Task LightingSchools-2009 EAp2: Minimum Energy Performanceposted by Maya Karkour on Aug 2, 2011, 10:45 am
Dear all, I received the following review comment for my school project: "Tables EAp2.4 and EAp2.5 report consumptions for process lighting for both cases, but it is unclear what... Last reply: Marcus Sheffer, Nov 21, 2011, 9:27 am |
|
Tenant area commissioningCS-2009 EAp1: Fundamental Commissioning of Building Energy Systemsposted by sompoche sirichote on Aug 16, 2011, 10:43 pm
Our project is an office building with 10 floors on the top are leased out as a hotel tenant and we are seeking for LEED CS certified. Last reply: Chris Ladner, Nov 21, 2011, 9:18 am |
|
transportation costNC-2009 MRc5: Regional Materialsposted by Scott West on Aug 31, 2011, 6:20 pm
I am working on a project which is being designed for a south pacific island. The majority of the construction materials do not exist on the island with the exception of rock. Fortunately, our... Last reply: Nadav Malin, Nov 21, 2011, 8:43 am |
|
PDF Template QuestionCI-2009 MRc4: Recycled Contentposted by elizabeth warlop on Sep 30, 2011, 6:52 pm
Hello, Last reply: Tristan Roberts, Nov 21, 2011, 1:36 am |
|
Confirmation of Case 1 Option 2 and DocumentationCI-2009 SSc3.3: Alternative transportation - parking availabilityposted by Raymond Loo on Aug 8, 2011, 12:50 am
To qualify for the 2 credit point here, we would only need to prove that there has been no parking provided or subsidized parking provided to our client (tenant)? For clarity, not tenants of the... Last reply: Tristan Roberts, Nov 21, 2011, 1:34 am |
|
Where do plumbing fixture uses, by occupancy type, come from?CI-2009 WEc1: Water Use Reductionposted by John ONeill on Sep 20, 2011, 2:56 pm
Does anyone know what the basis is for the plumbing fixture uses by occupancy type? For example - 3 water closet uses for each female... Last reply: Tristan Roberts, Nov 21, 2011, 1:33 am |
|
Electric Vehicle Charging StationsCI-2009 SSc3.3: Alternative transportation - parking availabilityposted by Susan F. on Jul 20, 2011, 8:45 pm
This project has 224... Last reply: Tristan Roberts, Nov 21, 2011, 1:31 am |
|
Exterior and Party WallsCI-2009 MRc1.2: Building reuse - maintain interior nonstructural elementsposted by Shirong Meng on Oct 31, 2011, 5:54 am
The elements of "Exterior and Party Walls" include shell or not? It seems to be exterior walls seperated from outdoor and party walls seperated from other spaces. But in the credit requirements,... Last reply: Tristan Roberts, Nov 21, 2011, 1:28 am |
|
cutsheets?CS-2009 MRc6: Certified Woodposted by Sara Neff on Jun 3, 2011, 7:33 pm
I'm confused on whether or not we need to provide product cutsheets, or if the invoices (line item, with dollar values and the... Last reply: Tristan Roberts, Nov 21, 2011, 1:15 am |
|
HVAC SystemCS-2009 EAc4: Enhanced Refrigerant Managementposted by Yolanda Sanchez on Jul 11, 2011, 1:41 pm
HVAC for the whole building is in the process of being designed (VRF system). We would like to know if the system can be installed in 2 stages, but we would like to submit the LEED certification... Last reply: Tristan Roberts, Nov 21, 2011, 1:12 am |