Forum quick links
Calculating 90% rainfall compliance
NC-2009 SSc6.2:Stormwater Design—Quality Controlposted by Simon Sue on
We're currently working on a high-rise commercial building, and hope someone could shed some lights on the following questions: 1.
HVAC on a green roof calculation
CS-2009 SSc7.2:Heat Island Effect—Roofposted by Petr Vogel on
Hello, we are working on the project of a new commercial building where green roof is about 50 % of the whole roof.
Documentation
NC-2009 MRc4:Recycled Contentposted by Maura Adams on
Do I need to enter every single material used into the spreadsheet, or can I stop once I've reached the 10% or 20% threshold? Please tell me it's the latter!
WEp1 - Children's Water Closets Water Use
NC-2009 WEp1:Water Use Reduction—20% Reductionposted by Ross Spiegel on
I am working on an elementary school project with flush valve type water closets sized for young children.
OPTION 3 - Survey Time
EBOM-2009 SSc4:Alternative Commuting Transportationposted by WAGNER OLIVEIRA SILVA on
We have same dubs about survey time.
Definition of Non-Structural Products and Materials
Pilot-Credits PC43:Certified Productsposted by Chloe Bendistis on
Hello, I cannot find a definition for "non-structural products and materials" and I was wondering if someone could point me in the right direction.
Naturally Ventilated Corridors
EBOM-2009 IEQp1:Minimum IAQ Performanceposted by Matthew Macko on
Do corridors need to have access to operable windows within 25 feet?
Material Values
CI-2009 MRc4:Recycled Contentposted by Holly Himes on
On the IDC Materials Calculator download from LEED-online states in footnote 2 that material value must "include all expenses to deliver the material to the project site, including taxes and delive
LEED NC 2.2 – Sunset Date
posted by Bryan Waters on
We have a project registered under LEED NC 2.2- After completion of Construction Documents of Phase 1; the project went on hold over a year ago. No submittals have been made to GBCI.
Modeling Multiple Buildings
NC-2009 EAp2:Minimum Energy Performanceposted by Santiago Rodriguez on
I am working on a new project which consists in 5 buildings, all have its own HVAC system designed, 3 of them have a complete HVAC, and the other 2 will only have Mechanical Ventilation to cool the