Table IEQc1-2 Outdoor Air Ventilation Rate
NC-2009 IEQc1:Outdoor Air Delivery Monitoringposted by Thomas Hellmann on
According to IEQc1, I am to complete table IEQc1-2 for all systems where 20% or more of the design supply airflow serves non-densely-occupied spaces.
LEED Pilot Credit 13-comment
Pilot-Credits PC13:Bicycle Network, Storage, and Changing Roomsposted by Alice Sung on
I appreciated Michael Smithing's clarificationof the defintion of a bicycle "network, " as inclusive of : " residential streets designed for a target speed of 25 mph (40 km/hr) or slower and comme
Fair price for off-site land conservation credits
EBOM-2009 SSc5:Site Development—Protect or Restore Open Habitatposted by Chris Draper on
Does anyone know the basic market price/acre or price/credit for securing contracts on off-site land that meets the SSc5 requirements?
Something might be helpful
posted by Diana Hill on
I had problem that cannot open leed online v3 on my mac for a long time, even though I already have the newest adobe reader version.
LEED CI 2009 : Project without HVAC change
posted by Diana Hill on
We are doing an interior renovation to an existing building. They plan to do only the interior upgrades and no change of the HVAC system.
Project without any HVAC change
NC-2009 PIf4:Schedule and Overview Documentsposted by Diana Hill on
We are doing an interior renovation to an existing building. They plan to do only the interior upgrades and no change of the HVAC system.
LEED Online 3.0 form
NC-2009 IEQc7.1:Thermal Comfort—Designposted by Noriko Nagazumi on
The IEQc7.2 Cooling Mode table asks for the Design Operative Temperature, Maximum Design Humidity and Design Air Speed for the four seasons (Spring, Summer, Fall, Winter).
Hand drier
CI-2009 MRc4:Recycled Contentposted by soha yamani on
hand drier installed in toilets : should it be included in materials ? if yes under which CSI division it is mentioned
Wall Finishes
CI-2009 MRc1.2:Building Reuse—Maintain Existing Interior Nonstructural Elementsposted by Laurie Hammack on
We have a project that is retaining most of the interior walls, but the walls are to receive new wall covering materials.
Eligibility
NC-2009 PIf1:Minimum Program Requirementsposted by PAWAN DAHIWAL on
I want to get LEED-EBOM certification for my book store (18,000 sq.ft) located on 3rd floor of total 12 floor building. can i eligible to get certification?