Passive House Certified Component vs Energy Star ProductsCI-2009 EAc1.3: Optimize energy performance - HVACposted by María Fernanda Aguirre on Aug 19, 2013, 11:42 am
Hi, I am currently working on an LEED for Commercial Interiors Project and the HVAC Engineer has just heard about some ventilation units with heat recovery which are certified as Passive House... Last reply: Marcus Sheffer, Aug 29, 2013, 9:21 am |
|
Option 1, Equipment Efficiency- Reuse of Existing EquipmentCI-2009 EAc1.3: Optimize energy performance - HVACposted by Tony Ricketts on Aug 12, 2013, 12:22 pm
Hi all, I have a tenant fit-out project served by water source HPs. Last reply: Dylan Connelly, Aug 16, 2013, 1:39 pm |
|
InsulationCI-2009 EAc1.3: Optimize energy performance - HVACposted by Catalina Caballero on Aug 14, 2013, 2:38 pm
Our project consist in a conversion from a warehouse to a university. but only part of the univeristy is being certified. Obviously as a warehouse the building didnt have any type of insulation... Last reply: Marcus Sheffer, Aug 16, 2013, 8:51 am |
|
Option 2: Insulation for Baseline and ProposedCI-2009 EAc1.3: Optimize energy performance - HVACposted by Saju Varghese on Aug 14, 2013, 4:05 pm
Under "LEED Project Submittal Tips: Commercial Interiors 2009", the guide is referencing to Table G3.1-5(F) when applicable for baseline and propose values consistent with Appendix A. Is this... Last reply: Tony Ricketts, Aug 15, 2013, 9:17 am |
|
Shading Devices in Baselin- Option 2. Energy Model.CI-2009 EAc1.3: Optimize energy performance - HVACposted by Saju Varghese on Jul 16, 2013, 10:55 am
Im a bit confused whether to use overhangs or not in the baseline of the energy model for option 2. Our project is large enough to have several windows, but its unclear if we need to leave or... Last reply: Catalina Caballero, Aug 14, 2013, 3:19 pm |
|
Energy Star AppliancesCI-2009 EAc1.3: Optimize energy performance - HVACposted by Saju Varghese on Jul 18, 2013, 9:28 am
Can savings be reflected on the energy model due to use of energy star appliances? Last reply: Dylan Connelly, Aug 13, 2013, 6:38 pm |
|
Percent Annual HVAC Energy Cost ReductionCI-2009 EAc1.3: Optimize energy performance - HVACposted by Saju Varghese on Aug 6, 2013, 6:22 pm
Which Cost reduction equation should be used on template when cooling plant has been updated with a high efficiency chiller and therefore proposed has been modeled including all the areas that... |
|
Uploads for EAC1.3-1CI-2009 EAc1.3: Optimize energy performance - HVACposted by Nick Chiarelli on Jun 21, 2013, 7:53 am
I plan to submit the Carrier HAP load data for Load calculations and an April load data for Part Load Calculations, but I am not sure what to include for the Fan sizing and zone-by-zone load... Last reply: Nick Chiarelli, Jul 9, 2013, 9:15 am |
|
LEED Interpretation #10134 as applied to fan coilsCI-2009 EAc1.3: Optimize energy performance - HVACposted by Silvia Ruiz on Jul 2, 2013, 1:26 pm
Hi, Would a project be eligible to apply for this credit if the scope of work includes the provision and installation of 100% of the fan coils serving the certifiable space, even if they... Last reply: Dylan Connelly, Jul 4, 2013, 2:33 pm |
|
Complete information on Variable Speed ControlCI-2009 EAc1.3: Optimize energy performance - HVACposted by Mike D on Jun 26, 2013, 7:07 am
There are no pumps or... Last reply: Dylan Connelly, Jun 26, 2013, 8:01 pm |