Industrial Site-Process WaterEBOM-2009 WEp1: Minimum Indoor Plumbing Fixture and Fitting Efficiencyposted by Dianne Herrin on Mar 26, 2010, 4:51 am
Hi -My building is an industrial site. They use substantial potable process water to "waterproof test" assembled product. I am presuming this does not need to be included here or in WEC2? Can... Last reply: Tristan Roberts, Mar 26, 2010, 11:03 am |
|
Partial RetrofitEBOM-2009 WEp1: Minimum Indoor Plumbing Fixture and Fitting Efficiencyposted by Tim Trefzer on Mar 23, 2010, 5:17 pm
I have a 55-story building that was built in 1991. 98% of the toilets and urinals are original, however 2% have been retrofit. All of the faucets have been retrofit with aerators. I have created... Last reply: Jason Franken, Mar 24, 2010, 10:11 am |
|
Efficiency calculationEBOM-2009 WEp1: Minimum Indoor Plumbing Fixture and Fitting Efficiencyposted by RASHID HAMEEN on Mar 16, 2010, 7:47 am
We are planing on pursuing LEEDS for one of our Garment manufacturing facilities. At the moment we are trying to see the status of our water usage compared to the baseline. We bought the... Last reply: Jason Franken, Mar 19, 2010, 12:08 pm |
|
Water Efficiency Calculation questionEBOM-2009 WEp1: Minimum Indoor Plumbing Fixture and Fitting Efficiencyposted by Bruce Truong on Feb 4, 2010, 11:18 am
HI, We are going at this LEED process ourselves here at Tufts Health Plan and I have a minor question regarding LEED baseline for shower heads. My question: We have about 1700 employees here... Last reply: Jenny Carney, Feb 7, 2010, 4:31 pm |