Slab on grade and concrete piersNC-2009 MRc1.1: Building reuse - maintain existing walls, floors and roofposted by David Browne on Sep 13, 2016, 12:37 pm
I have a large building with an arena at the second level. I am retaining the slab on grade on the first level except for some small cuts to run piping. On the first level are several concrete... Last reply: Tristan Roberts, Jan 18, 2017, 11:38 am |
|
Refurbishing of historic windowsNC-2009 MRc1.1: Building reuse - maintain existing walls, floors and roofposted by Kath Williams on May 31, 2016, 6:19 pm
Windows in our... Last reply: Megan White, Jan 17, 2017, 7:29 pm |
|
Curtain Wall Should Be Exterior Wall or Glazing?NC-2009 MRc1.1: Building reuse - maintain existing walls, floors and roofposted by Sara Zoumbaris on Jun 29, 2016, 3:23 pm
Is a large curtain wall to be considered as exterior wall or glazing for this credit? Thank You! Last reply: Megan White, Jan 17, 2017, 7:23 pm |
|
Curtain WallNC-2009 MRc1.1: Building reuse - maintain existing walls, floors and roofposted by Sara Zoumbaris on Jun 29, 2016, 3:22 pm
Would a curtain wall be considered exterior wall or glazing for this credit? Thanks! Last reply: Megan White, Jan 17, 2017, 7:16 pm |
|
Are basement walls included in envelope calculationsNC-2009 MRc1.1: Building reuse - maintain existing walls, floors and roofposted by Stacey Olson on Dec 7, 2016, 1:30 pm
I understand the floor slab of basements is allowed to be included; what about the envelope? I would think they should be allowable, as they provide a physical barrier to the elements, but I'm... Last reply: Megan White, Jan 17, 2017, 7:00 pm |
|
No floorNC-2009 MRc1.1: Building reuse - maintain existing walls, floors and roofposted by April Ambrose on Jun 13, 2016, 2:46 pm
A spec-built, cold-dark shell of a building was built with 4 walls and a roof, but the floor is still dirt. Now a client has purchased the building and will be fitting it out and adding a 20% sq... Last reply: Tristan Roberts, Jan 17, 2017, 6:55 pm |
|
Where to include stairs?NC-2009 MRc1.1: Building reuse - maintain existing walls, floors and roofposted by Stacey Olson on Dec 7, 2016, 5:17 pm
I don't see it mentioned in the Reference Guide for either MRc1.1 or MRc1.2, although I would think it was fall under MRc1.1. Thank you. Last reply: Tristan Roberts, Jan 17, 2017, 6:51 pm |
|
Historical BuildingNC-2009 MRc1.1: Building reuse - maintain existing walls, floors and roofposted by FABIO VIERO on May 18, 2016, 10:52 am
Hello everyone. Last reply: David Browne, May 18, 2016, 11:23 am |
|
Historic Bldg Renovation being done in phases, Bldg reuse calcsNC-2009 MRc1.1: Building reuse - maintain existing walls, floors and roofposted by Debra a. Lombard on Mar 24, 2016, 12:00 pm
I'm working on behalf of a... Last reply: Megan White, Mar 28, 2016, 2:39 pm |
|
Excluding AreasNC-2009 MRc1.1: Building reuse - maintain existing walls, floors and roofposted by Garrett Ferguson on Jan 14, 2016, 2:34 am
1. My question is about how to correctly exclude areas in these calcs. We are working on a large project that has been remodeled multiple times over the years, with asbestos present in various... |