Log in
Forum » NC-2009 MRc1.1
Topic

Slab on grade and concrete piers

NC-2009 MRc1.1: Building reuse - maintain existing walls, floors and roof
posted by David Browne on Sep 13, 2016, 12:37 pm

I have a large building with an arena at the second level. I am retaining the slab on grade on the first level except for some small cuts to run piping. On the first level are several concrete...

Last reply: Tristan Roberts, Jan 18, 2017, 11:38 am

Refurbishing of historic windows

NC-2009 MRc1.1: Building reuse - maintain existing walls, floors and roof
posted by Kath Williams on May 31, 2016, 6:19 pm

Windows in our...

Last reply: Megan White, Jan 17, 2017, 7:29 pm

Curtain Wall Should Be Exterior Wall or Glazing?

NC-2009 MRc1.1: Building reuse - maintain existing walls, floors and roof
posted by Sara Zoumbaris on Jun 29, 2016, 3:23 pm

Is a large curtain wall to be considered as exterior wall or glazing for this credit? Thank You!

Last reply: Megan White, Jan 17, 2017, 7:23 pm

Curtain Wall

NC-2009 MRc1.1: Building reuse - maintain existing walls, floors and roof
posted by Sara Zoumbaris on Jun 29, 2016, 3:22 pm

Would a curtain wall be considered exterior wall or glazing for this credit? Thanks!

Last reply: Megan White, Jan 17, 2017, 7:16 pm

Are basement walls included in envelope calculations

NC-2009 MRc1.1: Building reuse - maintain existing walls, floors and roof
posted by Stacey Olson on Dec 7, 2016, 1:30 pm

I understand the floor slab of basements is allowed to be included; what about the envelope? I would think they should be allowable, as they provide a physical barrier to the elements, but I'm...

Last reply: Megan White, Jan 17, 2017, 7:00 pm

No floor

NC-2009 MRc1.1: Building reuse - maintain existing walls, floors and roof
posted by April Ambrose on Jun 13, 2016, 2:46 pm

A spec-built, cold-dark shell of a building was built with 4 walls and a roof, but the floor is still dirt. Now a client has purchased the building and will be fitting it out and adding a 20% sq...

Last reply: Tristan Roberts, Jan 17, 2017, 6:55 pm

Where to include stairs?

NC-2009 MRc1.1: Building reuse - maintain existing walls, floors and roof
posted by Stacey Olson on Dec 7, 2016, 5:17 pm

I don't see it mentioned in the Reference Guide for either MRc1.1 or MRc1.2, although I would think it was fall under MRc1.1. Thank you.

Last reply: Tristan Roberts, Jan 17, 2017, 6:51 pm

Historical Building

NC-2009 MRc1.1: Building reuse - maintain existing walls, floors and roof
posted by FABIO VIERO on May 18, 2016, 10:52 am

Hello everyone.
I'm now working on a project under certification, according to LEED v2009 NC.
The project includes the restoration of an historical rural building, uninhabited and...

Last reply: David Browne, May 18, 2016, 11:23 am

Historic Bldg Renovation being done in phases, Bldg reuse calcs

NC-2009 MRc1.1: Building reuse - maintain existing walls, floors and roof
posted by Debra a. Lombard on Mar 24, 2016, 12:00 pm

I'm working on behalf of a...

Last reply: Megan White, Mar 28, 2016, 2:39 pm

Excluding Areas

NC-2009 MRc1.1: Building reuse - maintain existing walls, floors and roof
posted by Garrett Ferguson on Jan 14, 2016, 2:34 am

1. My question is about how to correctly exclude areas in these calcs. We are working on a large project that has been remodeled multiple times over the years, with asbestos present in various...