Log in
Forum » NC-2009 EAc2
Topic

Onsite renewable energy- Energy cost offset

NC-2009 EAc2: On-Site Renewable Energy
posted by Manikandan S on May 30, 2018, 1:34 am

Hi All

We are working in a project located in India which has an evaporative cooler as a cooling system, in the design submission review, the reviewer asked us to model the heating coil to...

Last reply: Marcus Sheffer, May 31, 2018, 11:14 am

Timing outsourced solar plan on-site / the building

NC-2009 EAc2: On-Site Renewable Energy
posted by Janine van den Kerkhof on Apr 23, 2018, 9:39 am

Hi All,

I have a question regarding the development of a new building on a existing plant. Prior to the construction a solar plant will be installed on-site (not a building) and connected...

Last reply: Marcus Sheffer, Apr 23, 2018, 11:42 am

Estimating the energy cost share of PV

NC-2009 EAc2: On-Site Renewable Energy
posted by Mohamed M. Abd Elhameed on Jun 6, 2017, 4:45 am

I am working on an industrial LEED project in KSA. Most of electrical loads are for the industrial processes itself (i.e production line), while the other remaining loads are for HVAC and...

Last reply: Marcus Sheffer, Jun 6, 2017, 11:58 am

Estimating the energy cost share of PV

NC-2009 EAc2: On-Site Renewable Energy
posted by Mohamed M. Abd Elhameed on Jun 6, 2017, 4:46 am

I am working on an industrial LEED project in KSA. Most of electrical loads are for the industrial processes itself (i.e production line), while the other remaining loads are for HVAC and...

Doubts in Green power & REC

NC-2009 EAc2: On-Site Renewable Energy
posted by SAMY Chamy on May 26, 2017, 1:21 am

Dear Concern:-

Our project have windmill, additionally wind mill capacity is 10 times greater than project connoted load

The project use government electricity with net metering...

Last reply: Marcus Sheffer, May 26, 2017, 11:24 am

EA Credit 2

NC-2009 EAc2: On-Site Renewable Energy
posted by Cristina Parenti on May 26, 2017, 5:52 am

Hello,
we are working on a project that intended to install solar panels on the roof but there isn't much room left for them.. The owner has several solar panel fields in the region (more...

Last reply: Marcus Sheffer, May 26, 2017, 10:53 am

Commissioning of PV system by different commissioning agent

NC-2009 EAc2: On-Site Renewable Energy
posted by Deborah Lucking on Apr 28, 2017, 6:08 pm

We have had this question come up a few times - the owner and the PV system supplier believe that it can be commissioned by a different...

Last reply: Marcus Sheffer, May 1, 2017, 9:06 am

Windmill

NC-2009 EAc2: On-Site Renewable Energy
posted by SAMY Chamy on Apr 27, 2017, 11:36 am

Dear Concern:-
Our client produce huge amount of Renewable energy by wind mills and the energy produced via wind mill is almost 5 times greater than LEED project annual energy consumption...

Last reply: Marcus Sheffer, May 1, 2017, 9:01 am

Wood pellets as a Renewable energy source

NC-2009 EAc2: On-Site Renewable Energy
posted by Vassil Vassilev on Aug 31, 2016, 8:04 am

We are at conceptual design stage for a new school building. The building will have its own boiler plant with oil fired burners as the only possible option available in the region.
While...

Last reply: Ward Miller, Sep 27, 2016, 11:09 pm

Planned/future Photovolatic installation

NC-2009 EAc2: On-Site Renewable Energy
posted by Stacey Olson on Aug 24, 2016, 8:09 pm

I'm working on a project that has installed the infrastructure to support a PV array, and is pursuing Enhanced Commissioning. They are working with various partners for funding of the actual...

Last reply: Marcus Sheffer, Aug 31, 2016, 12:37 pm