Time Window for Rework

LEED Reviews: Appeals, Design/Construction Submittals, and more
posted by  Jean Marais  on 

GBCI documentation says that one has 25 working days to respond to "Clarifications".

5
Tue Aug 13, 2013, 2:52 am

LEED Online seems to get worse as time goes on (over past 4 yrs)

Living with LEED Online - quirks, bugs and hiccups
posted by  Melissa Wrolstad  on 

Now LEED Online only works if I use a Chrome extension to Explorer - it does not work in regular Explorer anymore. Why is this the case?

5
Default Avatar
Senior Project Manager
CodeGreen Solutions
LEEDuser Basic Member
157 thumbs up
Mon Aug 12, 2013, 11:36 pm

SSc7.2 Weighted Average Calculator

NC-2009 SSc7.2:Heat Island Effect—Roof
posted by  Gabriel Moreno  on 

Apologies if this question has already been answered - but I've searched as thoroughly as possible and did not find a satisfiable explanation. I am running a simple test with the following values;

8
Default Avatar
Sustainability Architect
LEEDuser Basic Member
88 thumbs up
Mon Aug 12, 2013, 11:19 pm

LEED automation partners

Living with LEED Online - quirks, bugs and hiccups
posted by  Michael Beattie  on 

Our very limited experience, and the comments here, indicated that LEED Online is time-wasting, cumbersome, and unresponsive. Nearly dysfunctional.

3
principal
Joslin Consulting
LEEDuser Basic Member
140 thumbs up
Mon Aug 12, 2013, 10:51 pm

Kitchen Efficient Equipments

NC-2009 EAp2:Minimum Energy Performance
posted by  Marina Andrade  on 

Hi! How can i gain points in my simulation with kitchen equipments? I'm working on a project that has automation and i don't know how can i indicate this. I think all kitchen equipments will be

6
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4454 thumbs up
Mon Aug 12, 2013, 7:01 pm

Occupancy Sensor and/or Decorative lighting credit

CI-2009 EAp2:Minimum Energy Performance
posted by  Saju Varghese  on 

Could occupancy sensor credit under G.3.2 be used towards meeting the 10% lighting savings requirement? Could credit for decorative lighting be implemented as well 9.6.2a?

6
Mon Aug 12, 2013, 6:48 pm

ATM Machine

NC-2009 SSc2:Development Density and Community Connectivity
posted by  Wei Jiang  on 

Would anyone consider ATM machine as one of the basic services (Banks), for Option 2 - community connectivity?

3
LEED AP BD+C, O+M, Green Globes Professional
JLL
LEEDuser Basic Member
112 thumbs up
Mon Aug 12, 2013, 5:34 pm

Rainwater storage system

EBOM-2009 WEc3:Water Efficient Landscaping
posted by  Karin Wohlert  on 

I'm looking for a calculator or guide that would suggest how much rainwater could be collected in Mid-summer or the month with the highest irrigation demand.

3
Building Enclosure Consultant
BPL Enclosure
LEEDuser Basic Member
58 thumbs up
Mon Aug 12, 2013, 4:34 pm

Predominant spaces determined by square footage or hours of use?

NC-2009 EAp2:Minimum Energy Performance
posted by  Matt Scott  on 

I have a roughly 48,000 sf church with the following breakdown by area and hours of use: 1st Floor: 4,100 sf Multipurpose Space used 16 hours per week 8,200 sf Common Space used 72 hours per week

6
Default Avatar
Engineer
N.E. Fisher & Associates, Inc.
LEEDuser Basic Member
12 thumbs up
Mon Aug 12, 2013, 3:25 pm

Recertification

CI-2009 PIf5:Previously LEED Certified Details
posted by  David Wood  on 

Good morning, I had a question about recertification. My building is currently certified under V2.0 and we are up for recertification in 2015. We recieved certification in 2010.

7
Founder & CEO, LEED Fellow, BREEAM Fellow
BuildingWise LLC
LEEDuser Expert
224 thumbs up
Fri Aug 9, 2013, 6:31 pm