Forum quick links
Equipments to be commissioned
NC-2009 EAp1:Fundamental Commissioning of Building Energy Systemsposted by Alvaro Valdivia on
Hi: I have a boubt about the water heating equipment to be commissioned.
Current registered project shifts to New Rating Systems
posted by William Wong on
Could project currently registered under a rating system such as LEED NC 2009 opt to the new rating system such as LEED Data Centre at the time when the new rating system is available in 2012?
Information: Regional Priority Credit on International Projects?
CI-2009 EAc1.2:Optimize Energy Performance—Lighting Controlsposted by Raymond Loo on
My understanding is that an extra Regional Priority Credit can be earned on international projects here. Does anyone have any details to the actions required to get this RPC point?
Exempt compounds
NC-2009 IEQc4.2:Low-Emitting Materials—Paints and Coatingsposted by Paola Figueiredo, Newton Figueiredo on
The LEED´s definition of VOC should not be exclude the exempt compounds from the VOC content. However, according to the SCAQMD rules 1113 and 1168, the exempt compounds must be calculated.
Interior concrete stain
Schools-2009 IEQc4.2:Low-Emitting Materials—Paints and Coatingsposted by Chris Sanders on
Does interior concrete floor stain fall into the Floor Coatings category, with 100 g/L VOC?
0% Open Space Requirements
CS-2009 SSc5.2:Site Development—Maximize Open Spaceposted by Nándor Kovács on
I'm working on a project located in high density urban area which means 100% of the site can be built in the ground floor. How do i have to calculate 25% in this case?
Very good presentation,
posted by Nelina Loiselle on
Very good presentation, however I can not find the "Opt In" option on my GBCI My Credentials page? According to the presentation we have until Aug. 3rd as the first possible deadline date.