Laboratories - Appendix G Baseline System
NC-2009 EAp2:Minimum Energy Performanceposted by Adam Judge on
G3.1.1, Exception "d" requires laboratory spaces with a minimum of 5000 cfm of exhaust to use a baseline system type 5 or 7 that reduce the exhaust and makeup air volume to 50% of design values dur
SSc5.2 Project Boundary
NC-2009 SSc5.2:Site Development—Maximize Open Spaceposted by Christopher Widdowson on
If we are using a portion of adjacent Conservation Area to maximize the Open Space via a permanent easement, do we include the easement area within the Project Boundary on all documentation?
LTc4- Long-term bicycle storage, Bicycle maintenance program
Retail-CI-v4 LTc4:Bicycle facilitiesposted by Valentin Grimaud on
Hi, I am working on a store located on the groung floor of a mall.
ID+C - EQ Credit Interior Lighting - Lighting Sales areas
Retail-CI-v4 EQc6:Interior lightingposted by Valentin Grimaud on
HI, I am working on a store with two lighting types: furniture lighting and ambiant lighting. Only a part of the ambiant lighting is controlled depending on daylight illumination (40%).
Documentation DIBt AgBB - Wet applied product
NC-v4 EQc2:Low emitting materialsposted by Charline SEYTIER on
I have two support documents to justify the compliance of a wet applied product: - A sealed and signed DIBt notification confirming that the product is in accordance with the "Principles for the h
Definition of limited landscape opportunities
NC-2009 SSc5.1:Site Development—Protect or Restore Habitatposted by RETIRED on
I've checked the BD+C and O+M Reference Guides, the Addenda database, the v04 and v06 forms, and this forum to try and locate a definition for the "limited landscape opportunities" in relation to t
Outdoor Air Delivery Monitoring System for LEED CS building
CI-2009 IEQc1:Outdoor Air Delivery Monitoringposted by Ron Dean on
We have a leased office in a LEED C&S project.
Interior Lighting Quality
NC-v4 EQc6:Interior lightingposted by April Wang on
Regarding EQc6 option 2. I'm working towards satisfying strategies G and H. As part of the requirement, each space is to also meet the corresponding strategies E and F.
Regional Material for Reinforcement Steel
NC-2009 MRc5:Regional Materialsposted by sriram tetali on
Hi , As MRc5 credit Requirment says Raw material extraction and Manufacturing Plant of steel should be below 500 miles (800kms). But in our case the raw materials and manufacturing plant are locate
Local code offers voluntary option for no parking
NC-2009 SSc4.4:Alternative Transportation—Parking Capacityposted by Jeff Ross-Bain, PE, LEED Fellow, WELL AP on
We are working on a 50,000 ft2 medical office building (MOB) that is near a metro rail station. Local codes do not require buildings within 1,000 ft. of a rail station to provide parking.