water cooled chilller

NC-2009 EAp2:Minimum Energy Performance
posted by  sherif el adly  on 

Hi Marcus The building size is mandating to model the baseline with a water cooled chiller and I will compare the baseline with the design which is using HVAC that is (air cooled chiller + ice sto

1
Thu Dec 1, 2016, 5:40 pm

green power source

NC-2009 EAc6:Green power
posted by  sherif el adly  on 

The client have a solar park in a land adjacent to the land on which the project will be built.

1
Thu Dec 1, 2016, 7:10 pm

Substantial Completion, C of O, TCO

LEED Reviews: Appeals, Design/Construction Submittals, and more
posted by  Erika Duran  on 

Per the LEED certification Policy – we can submit construction review at Substantial Completion (defined as the date on which the building receives a Certificate of Occupancy or similar official in

1
Tue Dec 6, 2016, 9:38 pm

Use of Hycrete waterproofing admixture for Innovation credit

NC-2009 IDc1:Innovation in Design
posted by  Donna Juselis  on 

Our project is a mixed use redevelopment in a flood prone area. The first floor slab-on-grade on the project is located below the design flood elevation.

1
Fri Dec 16, 2016, 7:14 pm

Process temperature controlled space

NC-2009 IEQc6.2:Controllability of Systems—Thermal Comfort
posted by  Karen Elliott  on 

Hi I have a project where the temperature must be controlled automatically to ensure the manufactured product quality is maintained.

1
Sat Jan 7, 2017, 11:08 pm

Non Local Supplier

CS-2009 MRc6:Certified Wood
posted by  Jose Antonio Kovacevic  on 

Hi, We have a non local supplier.

1
Mon Aug 28, 2017, 2:53 pm

Modeling system serving both HVAC and Process

NC-v4 EAc2:Optimize energy performance
posted by  Visu Boj  on 

We are doing certification for a beverage factory. The factory requires chilled water for process load that is served by 2*1080 kW Evaporatively cooled Screw chillers.

1
Sun Dec 4, 2016, 8:36 pm

Lighting control for Meeting room

NC-2009 IEQc6.1:Controllability of Systems—Lighting
posted by  Thanh Le  on 

If a meeting room is designed with occupany sensor and manual override, does it comply with this credit. If it does not comply, how do we do to comply with this credit.

1
Tue Jan 10, 2017, 8:15 pm

Reference for the Total Daily Uses numbers

NC-2009 WEp1:Water Use Reduction—20% Reduction
posted by  Neshat Sakeena  on 

Hello, I was just wondering if anyone knows the reference or basis of the numbers used in Table 2. Default Fixture Uses, by Occupancy Type in the LEED manual?

1
Tue Dec 6, 2016, 8:57 am

Code is surpassing 90.1-2010

NC-v4 EAp2:Minimum energy performance
posted by  Amrit Kaur  on 

In a Jurisdiction where code is surpassing ASHRAE 90.1-2010 LEED buildings are required (by code) to meet the more stringent requirements but measure their energy score based improvement from ASHRA

1
Mon Dec 5, 2016, 3:12 pm