Forum quick links
Certification award beforem Grand opening??
posted by Soo young No on
We have finished design submittal and working on construction submittal. I am just wondering when would be good time to submit the submittal? Owner would like to have a certification flag(or some k
Using LEED -Schools 2009 templates for LEED Schools 2.0 resubmit
posted by Kevin Flynn on
Our project team is appealing a denied IEQp1 on a LEED Schools v2.0 project.
Design Appeal - PI Forms
posted by Erika Duran on
I am submitting an appeal for IEQp1 and uploaded new Mechanical Schedules to the PIf4 form to demonstrate that the inconsistencies that were present were due to a design change.
Appropriate time for submitting the Preliminary Design Review
posted by Shivani Langer on
What would be the recommended time/phase during a New Construction project when one should submit the preliminary design review?
Appeal extension or cancel appeal process?
posted by RICHARD CUEBAS on
We already entered in the appeal process and we are working on the appeal of prerequisites EAp2 & IEQp1 and credits EAc1, EAc2, IEQc7.1.
design phase review appeal
posted by Todd LaFreniere on
Our project is currently at the Construction Final Review Stage and we would like to submit an appeal on 2 of our Design credits. How is this done?
Failed LEED ND Stage 1 Prerequisite
posted by Bernard Sagaiyaraj on
I have received my LEED ND Stage 1 review results which contained 2 failed prerequisites. Can I proceed to Stage 2 and correct them there?
LEED v2.2 design credit re-evaluation during construction submit
posted by Susan Walter on
We are wrapping up a LEED v2.2. project and looking to submit for our construction review. The design credits have been through the process and the design review has been accepted.
Discrepancy between LEED form and scorecard on LEED Online
posted by Phil Meyer on
We are documenting 4 points for WEc1 Water Efficient Landscaping in the completed LEED online form (compliance button in form even notes 4 pts) for a LEED 2009 NC project.
Can I change the project name?
posted by Maria Porter on
Our project was registered a couple of years ago, we have passed precertification (CS), and we have passed Design phase.