Equipments to be commissioned

NC-2009 EAp1:Fundamental Commissioning of Building Energy Systems
posted by  Alvaro Valdivia  on 

Hi: I have a boubt about the water heating equipment to be commissioned.

2
Mechanical Engineer
POCH Ingenieria, Chile
LEEDuser Basic Member
10 thumbs up
Mon Aug 1, 2011, 2:19 pm

Information: Regional Priority Credit on International Projects?

CI-2009 EAc1.2:Optimize Energy Performance—Lighting Controls
posted by  Raymond Loo  on 

My understanding is that an extra Regional Priority Credit can be earned on international projects here. Does anyone have any details to the actions required to get this RPC point?

4
Principal
DNA GreenDesign
LEEDuser Basic Member
126 thumbs up
Sat Jul 30, 2011, 2:15 am

Exempt compounds

NC-2009 IEQc4.2:Low-Emitting Materials—Paints and Coatings
posted by  Paola Figueiredo, Newton Figueiredo  on 

The LEED´s definition of VOC should not be exclude the exempt compounds from the VOC content. However, according to the SCAQMD rules 1113 and 1168, the exempt compounds must be calculated.

2
Sustainability and Environment Director
PROSOCO, Inc.
LEEDuser Basic Member
126 thumbs up
Thu Jul 28, 2011, 6:46 pm

Interior concrete stain

Schools-2009 IEQc4.2:Low-Emitting Materials—Paints and Coatings
posted by  Chris Sanders  on 

Does interior concrete floor stain fall into the Floor Coatings category, with 100 g/L VOC?

2
Default Avatar
Design/LEED Specialist
The Neenan Company
LEEDuser Basic Member
133 thumbs up
Thu Jul 28, 2011, 5:15 pm

0% Open Space Requirements

CS-2009 SSc5.2:Site Development—Maximize Open Space
posted by  Nándor Kovács  on 

I'm working on a project located in high density urban area which means 100% of the site can be built in the ground floor. How do i have to calculate 25% in this case?

2
Default Avatar
Sustainability Team Leader
Obuda-Ujlak Zrt.
LEEDuser Basic Member
14 thumbs up
Thu Jul 28, 2011, 4:34 am

Steel structure enamel

NC-2009 IEQc4.2:Low-Emitting Materials—Paints and Coatings
posted by  javier bolanos zeledon  on 

Hi, this is a retrofit of an existing building where all the exterior structural walls are being replaced and also the interior walls.

2
Default Avatar
Director of Mechanical & Industrial Dept.
Dar Al-Handasah (Shair&Partners)S.A.L.
LEEDuser Basic Member
3 thumbs up
Wed Jul 27, 2011, 6:33 pm

SSc4 EBOM v2.2

EBOM-2009 SSc4:Alternative Commuting Transportation
posted by  Sheryl Swartzle  on 

Our project is 750,000 sf office with 1277 occupants. Project is located in Miami and has it's own parking garage.

4
Principal
Ackerstein Sustainability, LLC
LEEDuser Expert
545 thumbs up
Wed Jul 27, 2011, 1:43 pm

Calculating material costs in MRc4 and MRc5

NC-2009 MRc4:Recycled Content
posted by  Alexander Aaltonen  on 

I have similar concerns as Maria described earlier, and I would really appreciate some advice on how to calculate material costs in a case where a sub-contractor is performing concrete works on-sit

2
Wed Jul 27, 2011, 9:45 am

Greenhouse

Schools-2009 EAc1:Optimize Energy Performance
posted by  Lisa Logan  on 

Client is adding greenhouse to the school project - sort of late in the game. Does this space get included in our energy calcs? I am assuming yes and that there is no way around it.

3
LEED AP BD+C
Green Ideas
LEEDuser Basic Member
48 thumbs up
Tue Jul 26, 2011, 9:03 pm

Signage Details?

NC-2009 SSc4.4:Alternative Transportation—Parking Capacity
posted by  Marketing Coordinator  on 

Hi, I'm working on a LEED 2009 for Schools project and just rec'd my Design review comments.

2
Integrated Design & LEED Specialist
SERA Architects
LEEDuser Expert
1361 thumbs up