Lavatory Faucet default duration change during construcion.

NC-2009 WEc3:Water Use Reduction
posted by  BH .  on 

Hi, Due to "Water use reduction Additional Guidance" from July 14,2011 Nonresidential Default Lvatory Faucet duration has changed from 15 to 30 sec.

2
Mechanical Engineer
Integral Group
LEEDuser Expert
342 thumbs up
Tue Nov 22, 2011, 8:28 am

new project with old HVAC

NC-2009 EAp3:Fundamental Refrigerant Management
posted by  Timo Marquez  on 

I would like to know if the following complies with EAp3: We have a new construction (in process 2011) and the owner is purchasing an old HVAC systems that used R-12.

2
Default Avatar
Dir. Innovation
Green Soluce
LEEDuser Basic Member
13 thumbs up
Tue Nov 22, 2011, 5:02 am

Fenced playgrounds

Schools-2009 SSc5.2:Site Development—Maximize Open Space
posted by  Daniel McDonald  on 

We are working on an urban school renovation (SSc2=yes), and I am wondering if having the playgrounds and other outdoor areas behind fences affects this credit at all - are they still "pedestrian o

3
Mon Nov 21, 2011, 9:15 pm

LEED project defined boundary 1.5 buildings

CI-2009 EAc3:Measurement and Verification
posted by  Steve Khouw  on 

Just to be sure, to be sure, not trying to be picky here. Our new LEED-CI project encompasses 2 buildings, but only 1 is going to be fully occupied and the other only partially,

3
Principal
DNA GreenDesign
LEEDuser Basic Member
126 thumbs up
Mon Nov 21, 2011, 8:55 pm

Combine Option 1 and Option 2?

CS-2009 SSc4.3:Alternative Transportation—Low-Emitting and Fuel-Efficient Vehicles
posted by  Julie Hendricks  on 

Have any of you LEED experts out there ever done a combination of preferred parking spaces and alternative-fuel fueling stations?

2
Representative
Vermont House of Representatives
LEEDuser Expert
7780 thumbs up
Mon Nov 21, 2011, 5:13 pm

All Furniture to be Given to Another Company for Same Use.

CI-2009 MRc3.2:Materials Reuse—Furniture and Furnishings
posted by  Raymond Loo  on 

Instead of reusing all of its furniture (chairs, cabinets, cubicle walls, etc.) after the renovation, our client is giving all of it to another company that will use it as furniture. Would this qu

2
Senior Manager, Corporate Services
MEA & Associates Limited (Hong Kong)
LEEDuser Basic Member
62 thumbs up
Mon Nov 21, 2011, 4:55 pm

What are reviewers looking for in the section views

NC-2009 IEQc8.2:Daylight and Views—Views
posted by  Jean Marais  on 

I have provided plan views where it is assumed that one can't see over the shown case work, etc. I have provided elevations where one can see the height and size of windows.

4
Mon Nov 21, 2011, 4:49 pm

IEQp1 Corridor

NC-2009 IEQp1:Minimum IAQ Performance
posted by  Carolina Vergnano  on 

Hello, I'm working on a project that the air exchange in the corridor is made by an adjacent open plan office.

4
Principal, Energy and Engineering Leader
DLR Group | Westlake Reed Leskosky
LEEDuser Expert
267 thumbs up
Mon Nov 21, 2011, 4:41 pm

Confirmation of Case 1 Option 2 and Documentation

CI-2009 SSc3.3:Alternative Transportation—Parking Availability
posted by  Raymond Loo  on 

To qualify for the 2 credit point here, we would only need to prove that there has been no parking provided or subsidized parking provided to our client (tenant)?

3
Default Avatar
LEED AP
Hefferlin and Kronenberg Architects
LEEDuser Basic Member
20 thumbs up
Mon Nov 21, 2011, 6:34 am

PVmodules for generate of onsite renewable energy and REC

NC-2009 EAc2:On-Site Renewable Energy
posted by  Florian Schmidtchen  on 

For a NC manufacturing project we have been aproached by a company who would mount pv-modules on the building roof and sell them to building owner at no cost premium.

6
Mon Nov 21, 2011, 3:20 am