Forum quick links
Private vs. Public Lavatory Faucets
Schools-2009 WEp1:Water Use Reduction—20% Reductionposted by Alison Y Rivenburgh on
I am working on two elementary schools, and the lower grade levels have private restrooms intended for individual student use in each classroom.
School Kitchen Pre-Rinse and Wash Sinks
Schools-2009 WEp1:Water Use Reduction—20% Reductionposted by Art Irwin on
I am working on a high school project that includes a kitchen with both a pre-rinse sink and a three-tub sink that will have two faucets.
Lease agreement (signed by tenants)
CS-2009 IEQp1:Minimum IAQ Performanceposted by Rubén M. R. on
I'm working on a mixed-use CS project.
IAQ Testing method
NC-2009 IEQc3.2:Construction IAQ Management Plan—Before Occupancyposted by Adi Negara, LEED AP BD+C on
It's clear that for this credit, LEED only accepted IAQ testing using EPA or ISO method.
Facade lighting, Interior / exterior?
CS-2009 EAp2:Minimum Energy Performanceposted by Robert Gomez on
Hello, If facade lighting are installed at the perimeter inside the building, should this be considered interior or exterior LPD? These lights will be controlled / operated by the base building a
One-time potable water analysis
Pilot-Credits WEpc17:Cooling tower water useposted by WAGNER OLIVEIRA SILVA on
In the new version of Pilot credit Revised at 1/3/2012 they ask to be done one-time potable water analysis. How do we do if our project already covers 100% makeup water with non-potable water?
Tenant fit-out and C&S IEQ Credit 3
CS-2009 IEQc3:Construction IAQ Management Plan—During Constructionposted by Ricardo Sá on
Requirements of C&S IEQ Credit 3 also apply to tenants fit-out ?
Tenant Finish-Out Insulation
CS-2009 EAc1:Optimize Energy Performanceposted by Heather Holdridge on
We're working on a core and shell project and the owner is interested in not installing insulation, but having that as a tenant finish-out item.
Contradiction: Energy Modeling Area and certification fee area
NC-2009 EAc1:Optimize Energy Performanceposted by Diaa Madkour on
Hi all, we have a contradiction here between gross floor area of the energy modeling and the PIF2, in PIF2 we calculated the gross floor area as stated in GBCI : """ Project square footage for cer
Evapotranspiration data worldwide
NC-2009 WEc1:Water Efficient Landscapingposted by Susann Geithner on
The new guidance for international projects also includes a resource for evapotranspiration data worldwide.