Humidity is out of Our Control, Can we still achieve credit?

CI-2009 IEQc7.2:Thermal Comfort—Verification
posted by  Krystle Thomsen  on 

My company is going to be a tenant in a new space where will not have the capability to increase/introduce humidity as we are tying into the Building Management System.

3
Representative
Vermont House of Representatives
LEEDuser Expert
7780 thumbs up
Tue Mar 11, 2014, 6:07 pm

Re carpeting 50,000+ sq feet not count?

EBOM-2009 MRc3:Sustainable Purchasing—Facility Alterations and Additions
posted by  Victoria Bauer  on 

Hi there, I am unsure what is meant by one specialty trade. I have a project that is considering re carpeting about half of their building, which is a substantial alteration. Would this not count?

3
Tue Mar 11, 2014, 3:11 pm

Single Family Residential Villa 4500 Sqm (G+1),

CS-2009 PIf1:Minimum Program Requirements
posted by  Mohd Imran Shaikh  on 

Hi There, Clients wants to attain LEED for Silver Certification for its Villa. Note that the Villa is 4500 sqm and meets the minimum floor area requirement.

4
Representative
Vermont House of Representatives
LEEDuser Expert
7780 thumbs up
Tue Mar 11, 2014, 12:18 pm

Senior living facility

ND-v2009 NPDp3:Connected and open community
posted by  Susan Di Giulio  on 

We have a very large site (609 acres), a lot of which is non-buildable land (open space, wetlands, slopes).

2
LEED AP-ND, Principal
Criterion Planners
LEEDuser Expert
231 thumbs up
Tue Mar 11, 2014, 4:52 am
3
Sustainability Consultant
ECOstudio XV LTD
LEEDuser Basic Member
1 thumbs up
Mon Mar 10, 2014, 6:40 pm

Performance period for leakage rate

EBOM-2009 EAc5:Enhanced Refrigerant Management
posted by  American University  on 

I'm wondering what performance period would be acceptable for calculating the leakage rate (lbs of refrigerant added and over what time frame) for this credit.

4
Mon Mar 10, 2014, 3:01 pm

Future HVAC Installation

CS-2009 EAp3:Fundamental Refrigerant Management
posted by  Curt Pascoe  on 

What if your CS building scope does not include HVAC equipment (and therefore no refrigerants)? USGBC requires the entire building to meet this prereq (including tenant spaces).

3
Default Avatar
Built Environment Professional
Built Kansas City LLC
LEEDuser Basic Member
28 thumbs up
Mon Mar 10, 2014, 2:21 pm

MPR 6

CI-2009 EAc3:Measurement and Verification
posted by  Adrienn Gelesz  on 

I have tried to figure out but cannot wrap my head around another subject. MPR 6 requires sharing actual whole-project energy and water usage data for a period of at least 5 years.

4
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4454 thumbs up
Sat Mar 8, 2014, 4:06 am

Rainwater Management in Colorado

EBOM-v4 SSc2:Rainwater management
posted by  Jonathan Miller  on 

Does anyone know what the rules are on engaging in rainwater management in Colorado? I'm under the impression that this is against the law in the state.

3
Sat Mar 8, 2014, 3:44 am

Exterior covered spaces

NC-2009 PIf2:Project Summary Details
posted by  Esmeralda Ward  on 

Hello, Could someone please clarify where exterior hardscape spaces that are covered by the building roof should be counted?

4
Fri Mar 7, 2014, 7:14 pm