Playing fields exclusion

NC-2009 WEc1:Water Efficient Landscaping
posted by  FRAGKISKOS LEVANTIS  on 

Projects other than Schools: Can they exclude playing fields in certain credits just like Schools can?

2
Representative
Vermont House of Representatives
LEEDuser Expert
7780 thumbs up
Wed Mar 26, 2014, 7:56 pm

Submetering for AHUs with multiple tanents

CS-2009 EAc5.2:Measurement and Verification—Tenant Submetering
posted by  Jatuwat Varodompun  on 

We have an hi-rise office building with Chiller and AHUs system. We plan to 3 AHUs per floor. 1.

5
Wed Mar 26, 2014, 1:00 pm

Future space

CS-2009 EAc1:Optimize Energy Performance
posted by  Jatuwat Varodompun  on 

In case of project with an area which is already designed but yet built (less than 40% of gross project area), can we use "owner's commitment" instead of "leasing agreement" to state all the design

2
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4454 thumbs up
Wed Mar 26, 2014, 6:21 am

Building with no parking

NC-2009 SSc4.3:Alternative Transportation—Low-Emitting and Fuel-Efficient Vehicles
posted by  John Riker  on 

I am working on an existing building in a commercial core. The building has no parking lot, but there is leasable parking spots in the vicinity.

3
Tue Mar 25, 2014, 11:20 pm

Fundamental commissioning of the base building

CS-2009 EAp1:Fundamental Commissioning of Building Energy Systems
posted by  eileen hughes  on 

General Contractor is working on the base building, which is required to be LEED CS certified.

3
Regional Director
Integral Group
LEEDuser Basic Member
0 thumbs up
Tue Mar 25, 2014, 8:17 pm

Education Program - what if project is private?

NC-2009 IDc1:Innovation in Design
posted by  Crista Shopis  on 

The nature of my clients building is private. They would be unwilling to host tours from the public or include too much information on a public website.

2
LEED Fellow
Integrated Design + Energy Advisors, LLC
LEEDuser Expert
377 thumbs up
Tue Mar 25, 2014, 7:52 pm

De-lamping

CI-2009 EAc1.1:Optimize Energy Performance—Lighting Power
posted by  Sunayana Jain  on 

Can de-lamping be acceptable to meet the Lighting Power Density Requirements?

3
Tue Mar 25, 2014, 6:51 pm

Combination of Option 1&2

NC-2009 SSc4.3:Alternative Transportation—Low-Emitting and Fuel-Efficient Vehicles
posted by  V B  on 

I have seen a similar post to this in 2012 and I was wondering if anyone has since then successfully implemented this strategy by using a combination of fueling stations and preferred parking for f

10
Default Avatar
Architect
RB+B Architects
LEEDuser Basic Member
0 thumbs up
Tue Mar 25, 2014, 6:28 pm

Regional Priority Credits - Outside US Projects

EBOM-2009 RPc1:Regional Priority
posted by  Sundararaj Subburaman  on 

My project is located in 411045 in Pune, India. It is not listed in the EBOM spreadsheet tab and does not appear using the "Find" function.

2
Representative
Vermont House of Representatives
LEEDuser Expert
7780 thumbs up
Tue Mar 25, 2014, 1:54 am

Regional points for EAc1 - Optimize Energy Performance

NC-2009 RPc1:Regional Priority
posted by  Mariah Grife  on 

My project has EA c1 listed as a possible Regional Priority credit. This credit allows 1-19 points, does my project apply for a Regional credit if I get even (1) point on EAc1?

6
LEED AP BD+C, O+M, Green Globes Professional
JLL
LEEDuser Basic Member
112 thumbs up
Mon Mar 24, 2014, 5:47 pm