Over limit adhesive used while building is open

CS-2009 IEQc4.1:Low-Emitting Materials—Adhesives and Sealants
posted by  Jayme Antolik  on 

I am on a project where the contractor used an adhesive that exceeds the VOC limit for that type but the building was open when they used it.

1
Fri Jun 2, 2017, 12:47 pm

Process water and residential units

NC-v4 WEp2:Indoor water use reduction
posted by  MAUDE PINTAL  on 

Our project includes a community center and a multi-residential part.

0

Active freight rail

Warehouses-NC-v4 LTc4:Surrounding density and diverse uses
posted by  Yong Lee Low  on 

Hi, in my country, we do not have freight rail (or railway to transport cargo from my understanding). We only transport cargo by ship or by plane.

1
Sat Aug 26, 2017, 2:09 pm

Different CxA for Construction other than one hired duringDesign

CS-v4 EAc1:Enhanced commissioning
posted by  mohammad Hassan  on 

Can a different CxA for a project Construction Phase be hired other than the one hired during Design Phase ?

1
Wed Aug 16, 2017, 12:18 am

Acoustic performance: reverberation time

NC-v4 EQc9:Acoustic performance
posted by  alessandro santuari  on 

Hi, we have a project with large waiting rooms: are there specific values for "Reverberation time requirements", as there are not similar room type in the table 2 of reference guide? Thanks

1
Tue Sep 26, 2023, 2:25 pm

Airport Terminal LEED certification

Healthcare-v2009 MPR3:Must use a reasonable site boundary
posted by  KONSTANTINOS VAVALETSKOS  on 

In an airport LEED project, only the terminal building is going to be certified. In this case how the LEED Boundary should be defined?

1
Sat Aug 26, 2017, 9:06 pm

Alternative Compliance Path

NC-v4 EAc2:Optimize energy performance
posted by  Gabriela Mena   on 

Hi, We are working in a Core and Shell project that was registered after april, 2016, from that date to comply with the pre requisite we need to achieve at least 14% savings, We want to know if th

1
Thu Jun 1, 2017, 6:19 pm

Alternative Compliance Path

CS-2009 EAc1:Optimize Energy Performance
posted by  Gabriela Mena   on 

Hi, We are working in a Core and Shell project that was registered after april, 2016, from that date to comply with the pre requisite we need to achieve at least 14% savings, We want to know if the

1
Thu Jun 1, 2017, 6:35 pm

System Type 9 Baseline Fan Sizing

NC-2009 EAp2:Minimum Energy Performance
posted by  Brian Kenney  on 

I am working on a job with the Army Corps of Engineers that has a vehicle maintenance workbay with general exhaust requirements of 1.5 CFM/SF dictated by the RFP.

1
Fri Jun 2, 2017, 1:48 pm

Bus Line Rerouting for Adjacent Bridge Construction

NC-2009 SSc4.1:Alternative Transportation—Public Transportation Access
posted by  Kevin McNulty  on 

Hi. My firm is working on a building that will be located right at the foot of a large bridge project that is currently in construction (estimated reopening in a few years).

1
Thu Sep 14, 2017, 4:06 pm