Off-site PV farm financed by property owner

EBOM-2009 EAc4:On-Site and Off-Site Renewable Energy
posted by  Dricka Brown Thobois  on 

I am working with a property who is going for LEED EBOM recertification.  The property is owned by a large business that has financed, owns, and maintains, a very large PV farm on the wes

1
Mon Jul 23, 2018, 8:15 pm
2
Default Avatar
Founder and CEO
Greenwave Global Consulting (GGC)
LEEDuser Basic Member
8 thumbs up
Fri May 25, 2018, 12:44 am

LEED EBOM EA c.4

EBOM-2009 EAc4:On-Site and Off-Site Renewable Energy
posted by  Fabio Frescia  on 

Hello, I have a LEED EBOM project in Thailand. I am now dealing with EA c.4 - On site or Off site Renewable Energy.

1
Fri Oct 16, 2015, 3:18 pm
1
Thu Aug 26, 2010, 8:18 pm

On-site vs. Off-Site Campus Project

EBOM-2009 EAc4:On-Site and Off-Site Renewable Energy
posted by  Eddie Cuevas  on 

I am working on an EBOM project located on a college campus.

1
Fri Aug 30, 2013, 3:26 pm

Certificates for hot district water?

EBOM-2009 EAc4:On-Site and Off-Site Renewable Energy
posted by  Izabela Kwiecinska  on 

Hello Everyone, We are preparing our Client to buy Green-e certified energy. We don't know if he has to buy also GOs or carbon offsets for district hot water that the building is supplied with.

1
Tue Aug 29, 2017, 7:01 pm

EAc4:Purchased REC's

EBOM-2009 EAc4:On-Site and Off-Site Renewable Energy
posted by  gwenedd murray  on 

This pertains to REC's purchased at the corporate level: My project is a large office building with multiple tenants.

1
Fri Apr 22, 2011, 11:26 pm

Performance Period Question for PV, SREC and credis added at end

EBOM-2009 EAc4:On-Site and Off-Site Renewable Energy
posted by  Bahareh van Boekhold  on 

I have a similar question as Summer Gorder. We are at the cusp of Gold certificaion. If we will be 1-2 credit short after GBCI review PV isnatllation can be justified at the buillding.

0

EBOM 2009, EAc4 - LEED Form Calculations for On-site?

EBOM-2009 EAc4:On-Site and Off-Site Renewable Energy
posted by  Sara Zoumbaris  on 

This question is in regards to the LEED online form for SSc4 in EBOM 2009. We have selected the option to calculate for "On-Site" renewable energy.

1
Tue Mar 19, 2013, 6:37 pm

Calculating total energy use for RECs purchase

EBOM-2009 EAc4:On-Site and Off-Site Renewable Energy
posted by  Charalampos Giannikopoulos  on 

Since the RECs (or equivalent) needs to meet 100% of the building’s energy use (in case of pursuing 6 points) does this mean that we need to wait until full completion of the performance period in

1
Tue Dec 1, 2015, 10:00 pm