Fluch Out Complete - Fire Happened Near Building
NC-2009 IEQc3.2:Construction IAQ management plan - before occupancyposted by Sara Zoumbaris on
We have a facility that has been complete and turned over to the owner for a few months but has not yet been occupied; the building is waiting for all furniture to be delivered and put into place.
Residential Flush out Requirements
NC-2009 IEQc3.2:Construction IAQ management plan - before occupancyposted by Rachel Manoguerra on
I've seen two other people ask this question, but can't find that it's been answered. So sorry, if I'm asking an already answered question.
IAQ Flush Out
NC-2009 IEQc3.2:Construction IAQ management plan - before occupancyposted by J Morrison on
I would like to know what documentation is acceptable to USGS on the flush out process? Is there documentation from the BAS system required?
Air Testing Requirements - TICs
NC-2009 IEQc3.2:Construction IAQ management plan - before occupancyposted by Chad Mapp on
Our team decided to perform air quality testing before occupancy on a recently completed building. We have had some question over which method is required for tVOC testing and for what compounds.
Air Quality Testing - Elevator Lobbies in Parking Garage
NC-2009 IEQc3.2:Construction IAQ management plan - before occupancyposted by Katherine Wilde on
Our project has 4 garage levels. There are 3-4 elevator lobbies on each level. The lobbies are small and receive OA from RTUs serving the offices above.
Option 1 Path 2 Mechanical & Electrical Rooms
NC-2009 IEQc3.2:Construction IAQ management plan - before occupancyposted by Amy Harmon on
I am working on a project that has multiple AHUs serving different types of spaces and we also have several large mechanical and electrical rooms.
Option 2-Air Testing - Building with Phased Completion
NC-2009 IEQc3.2:Construction IAQ management plan - before occupancyposted by Lilian Seow on
We r building 424 residential units - 46 storeys high tower.
Permanent furniture
NC-2009 IEQc3.2:Construction IAQ management plan - before occupancyposted by Pascal Genest-Richard on
We would like to know if it is possible to start the flush out (and maybe even finish it) before all permanent furniture is installed.
Testing with multiple systems in one space
NC-2009 IEQc3.2:Construction IAQ management plan - before occupancyposted by Nate Steeber on
I've looked deeply into all the comments here, but I can't seem to find an answer - I apologize if this is a repeat, or too simple of a question: My project has many AHUs, in some cases two differ