3rd Party Independent Reviewer as Enhanced CxA
NC-2009 EAc3:Enhanced Commissioningposted by Lesley Treacy on
Hi, I have read through the comments and understand the requirements for the Enhanced Commissioner to be a 'disinterested' or 'independent' body.
CxA Appointment
NC-2009 EAc3:Enhanced Commissioningposted by Ameet AA on
Project type: School Academy LEED Rating: New Construction 2009 for School, AGMBC 2010 Approach Hi my company is providing LEED Assessment, Architectural as well as MEP consultancy to School Pro
The same CxA overseeing EAc3 tasks must ALSO oversee EAp1?
NC-2009 EAc3:Enhanced Commissioningposted by Brooks Critchfield on
Footnote #4 on page 221 of the LEED-NC v2009 Reference Guide expressly notes that "The same CxA overseeing the enhanced commissioning tasks must also oversee the fundamental commissioning tasks."
operating instructions for the "integrated building systems" ??
NC-2009 EAc3:Enhanced Commissioningposted by Tom Kennedy on
LEED for Schools 2007 and BD+C (v3-2009) both refer to this in the required documents within the Systems Manual.
Enhanced Commissioning for a VRF small system
NC-2009 EAc3:Enhanced Commissioningposted by J.R. Anderson on
When uploading the detail information collected for the enhanced commissioning the details the LEED reference material referenced in the 2009 fundamentals section (step 9) spells out items that are
Changing CxA agents after Final Design
NC-2009 EAc3:Enhanced Commissioningposted by Elle Brown on
Due to issues with the contract and how our project was funded, we may be forced to get a new CxA to continue the project after final design.
Separate Heating and Cooling District Energy Systems
NC-2009 EAc3:Enhanced Commissioningposted by James Del Monaco on
Our project is located on a University campus with two separate DES buildings. One DES building houses all the chilled water equipment including chillers, pumps, cooling towers, etc.
Commissioning of Systems not required in prereq
NC-2009 EAc3:Enhanced Commissioningposted by Shauna Sproul on
Can points be achieved in innovation and design for commissioning of systems not required in prereq, for example the building envelope? I understand 2012 is addressing this, but what about 2009? I
CxA designation question
NC-2009 EAc3:Enhanced Commissioningposted by Blas Beristain on
Hello! We are involved in a project of a new headquarters of an architectural firm. In this project, the owner will be the architectural firm.
CxA Contract Question
NC-2009 EAc3:Enhanced Commissioningposted by Mark Haynie on
We hold a contract for construction of a project as the General Contractor. We also have contracted with the design firm (Architect) for the project.