3rd Party Independent Reviewer as Enhanced CxA

NC-2009 EAc3:Enhanced Commissioning
posted by  Lesley Treacy  on 

Hi, I have read through the comments and understand the requirements for the Enhanced Commissioner to be a 'disinterested' or 'independent' body.

2
Representative
Vermont House of Representatives
LEEDuser Expert
7780 thumbs up
Tue Nov 27, 2012, 2:15 pm

CxA Appointment

NC-2009 EAc3:Enhanced Commissioning
posted by  Ameet AA  on 

Project type: School Academy LEED Rating: New Construction 2009 for School, AGMBC 2010 Approach Hi my company is providing LEED Assessment, Architectural as well as MEP consultancy to School Pro

4
LEED Fellow
Integrated Design + Energy Advisors, LLC
LEEDuser Expert
377 thumbs up
Mon Nov 5, 2012, 5:09 pm

The same CxA overseeing EAc3 tasks must ALSO oversee EAp1?

NC-2009 EAc3:Enhanced Commissioning
posted by  Brooks Critchfield  on 

Footnote #4 on page 221 of the LEED-NC v2009 Reference Guide expressly notes that "The same CxA overseeing the enhanced commissioning tasks must also oversee the fundamental commissioning tasks."

4
Mon Sep 17, 2012, 7:24 pm

operating instructions for the "integrated building systems" ??

NC-2009 EAc3:Enhanced Commissioning
posted by  Tom Kennedy  on 

LEED for Schools 2007 and BD+C (v3-2009) both refer to this in the required documents within the Systems Manual.

2
LEED Fellow
Integrated Design + Energy Advisors, LLC
LEEDuser Expert
377 thumbs up
Mon Jul 2, 2012, 3:30 pm

Enhanced Commissioning for a VRF small system

NC-2009 EAc3:Enhanced Commissioning
posted by  J.R. Anderson  on 

When uploading the detail information collected for the enhanced commissioning the details the LEED reference material referenced in the 2009 fundamentals section (step 9) spells out items that are

2
LEED Fellow
Integrated Design + Energy Advisors, LLC
LEEDuser Expert
377 thumbs up
Wed Jun 6, 2012, 4:04 pm

Changing CxA agents after Final Design

NC-2009 EAc3:Enhanced Commissioning
posted by  Elle Brown  on 

Due to issues with the contract and how our project was funded, we may be forced to get a new CxA to continue the project after final design.

3
Fri May 11, 2012, 6:24 pm

Separate Heating and Cooling District Energy Systems

NC-2009 EAc3:Enhanced Commissioning
posted by  James Del Monaco  on 

Our project is located on a University campus with two separate DES buildings. One DES building houses all the chilled water equipment including chillers, pumps, cooling towers, etc.

3
Default Avatar
Sustainability Director, PE
P2S Engineering, Inc.
LEEDuser Basic Member
48 thumbs up
Wed May 9, 2012, 3:10 pm

Commissioning of Systems not required in prereq

NC-2009 EAc3:Enhanced Commissioning
posted by  Shauna Sproul  on 

Can points be achieved in innovation and design for commissioning of systems not required in prereq, for example the building envelope? I understand 2012 is addressing this, but what about 2009? I

2
LEED Fellow
Integrated Design + Energy Advisors, LLC
LEEDuser Expert
377 thumbs up
Fri Mar 23, 2012, 9:16 pm

CxA designation question

NC-2009 EAc3:Enhanced Commissioning
posted by  Blas Beristain  on 

Hello! We are involved in a project of a new headquarters of an architectural firm. In this project, the owner will be the architectural firm.

5
Sustainability Manager
YR&G
LEEDuser Basic Member
55 thumbs up
Fri Mar 23, 2012, 8:57 pm

CxA Contract Question

NC-2009 EAc3:Enhanced Commissioning
posted by  Mark Haynie  on 

We hold a contract for construction of a project as the General Contractor. We also have contracted with the design firm (Architect) for the project.

2
Default Avatar
Commissioning Engineer
LEEDuser Basic Member
15 thumbs up
Fri Mar 23, 2012, 8:52 pm