Baseline System configuration for mixed use condominium

NC-2009 EAp2:Minimum Energy Performance
posted by  Jason Biondi  on 

We are working on a 10 story mixed use building consisting of approx.

1
Sun Nov 2, 2014, 11:51 pm

40% WWR does it include the wall connected to other building?

NC-2009 EAp2:Minimum Energy Performance
posted by  Haojie Wang  on 

I wonder if the wall is directly connected to adjacent building ,should we include them in the window to wall calculation?

1
Tue Jun 14, 2016, 2:01 pm

Outdoor Air Intake: Baseline vs. Proposed

NC-2009 EAp2:Minimum Energy Performance
posted by  Ricardo Sá  on 

We are currently working on a LEED project whose Baseline Building will have an HVAC system 5 installed.

1
Mon Nov 12, 2012, 2:46 pm

Baseline HVAC schedules

NC-2009 EAp2:Minimum Energy Performance
posted by  Vernon Smith  on 

The project will apply for certification under LEED v2009 NC. The Proposed design is a 50,000 sf three story building (two above ground plus a full basement) with a central atrium.

1
Mon May 8, 2017, 2:23 pm

Garage Lighting LPDs

NC-2009 EAp2:Minimum Energy Performance
posted by  Joseph Snider  on 

ASHRAE lists .2 w/sf for garage spaces in Space by Space, and .3 w/sf in Building Area method.

1
Tue Sep 15, 2015, 10:02 pm

Energy Modeling

NC-2009 EAp2:Minimum Energy Performance
posted by  Muzammal Abbas LEED AP (BD+C)  on 

Hi everyone, I am doing energy modeling for my project in Pakistan and i want to need some clarification and help from seniors: 1) Is it true that for baseline and proposed case HVAC system shoul

1
Wed Jun 29, 2016, 2:05 pm

Base case system for high equipment loads spaces

NC-2009 EAp2:Minimum Energy Performance
posted by  Nandana Kumar  on 

The project is a 67000 sqft, six floored building. There are rooms with high equipment loads of greater than 20W/sft . The total area of these type of rooms adds up to 14,000 sqft.

1
Tue Dec 4, 2012, 2:42 pm

Hotel key tag system

NC-2009 EAp2:Minimum Energy Performance
posted by  Nandana Kumar  on 

We are working on a hotel project. The guest rooms have a key tag system where the lights and AC switches off as soon as the guest removes the key from the key slot.

1
Tue Mar 25, 2014, 2:36 pm
1
Mon Jun 21, 2010, 1:34 pm

Fan cycling in System 1/2

NC-2009 EAp2:Minimum Energy Performance
posted by  Haojie Wang  on 

I have a question about fan cycling for system 1 in residential units. G3.1.2.4 says fan should be on whenever space is occupied. Does this applies to residential units?

1