Forum quick links
Who is the Commissioning Authority?
NC-2009 EAp1:Fundamental Commissioning of Building Energy Systemsposted by Heather Holdridge on
We have one firm performing fundamental Cx services and another firm performing enhanced Cx services. Which consultant would be designated the "commissioning authority?"
Signatories
NC-2009 EAp1:Fundamental Commissioning of Building Energy Systemsposted by Michelle Rosenberger on
With LEED 2009 came mandatory online signatories for Owner, CxA, Contractor, etc.
Innitial ?
NC-2009 EAp1:Fundamental Commissioning of Building Energy Systemsposted by Eric JS on
Dear all, In some credits, including in CxA credit, there are initial of CxA or other parties are required.
Commissioing of Process Energy Use
NC-2009 EAp1:Fundamental Commissioning of Building Energy Systemsposted by Bill Holub on
Thanks in advance. I have seen conflicting directions on whether and which process system need to be Cx'ed.
uploading OPR and BOD in the LEED On-Line
NC-2009 EAp1:Fundamental Commissioning of Building Energy Systemsposted by Benjie Herrera on
Who is allowed to upload the OPR and BOD in the LEED On-Line?When can we upload these documents ?
CxA Experience
NC-2009 EAp1:Fundamental Commissioning of Building Energy Systemsposted by Ameet AA on
LEED online template/ form require the following: "Enter information for two projects commissioned by the CxA which are similar in scope and type to this LEED project building" I am working on L
Partial Commissioning at the time of submission
NC-2009 EAp1:Fundamental Commissioning of Building Energy Systemsposted by Maya Karkour on
Hi, LEED allows to submit for Commissioning if 2 systems are completely commissioned. LEEDOnline differentiates between "Lighting Controls" and "Daylighting Controls".
Commissioning for NC Tenant Fit-outs
NC-2009 EAp1:Fundamental Commissioning of Building Energy Systemsposted by Carly Ruggieri on
A project of mine is a high-rise residential building with 6 floors of commercial spaces that will be fit-out by future tenants.
Standard PV commissioning?
NC-2009 EAp1:Fundamental Commissioning of Building Energy Systemsposted by Jared Silliker on
Does anybody have a standard checklist or list of data points for commissioning a PV system? Related, is it OK for a CxA to ask the PV sub to gather data for Cx purposes vs.
Commissioning Walk-in Freezers / Coolers
NC-2009 EAp1:Fundamental Commissioning of Building Energy Systemsposted by Richard Woodward on
We have a mixed use new office / commercial kitchen project with owner occupiers.