Option 2 IAQ Testing

NC-v4 EQc4:Indoor air quality assessment
posted by  Robert Cashins  on 

Are there guidelines on how to determine how many air samples need to be collected to comply with the IAQ Assessment requirement?

2
Sustainability Design Leader, Exhibit Designer, Associate
CambridgeSeven
LEEDuser Premium Member
9 thumbs up
Wed Jun 26, 2024, 8:49 pm

Pressurized entryway vestibules at high-volume building entrances

Healthcare-v4 EQc1:Enhanced indoor air quality strategies
posted by  Priscillia Champagne  on 

Hi, I would like to know if there is additional guidance on the requirement to provide pressurized entryway vestibules at high-volume building entrances.

5
Default Avatar
LEEDuser Premium Member
1 thumbs up
Thu Jun 27, 2024, 4:19 pm

Heat Island Reduction

NC-v4 SSc5:Heat island reduction
posted by  Jose Castorena  on 

In this credit under option 1 the standard formula includes a vegetated roof.

2
Managing Partner
Ecoimpact Consulting
LEEDuser Expert
171 thumbs up
Thu Jun 27, 2024, 4:05 pm

Flush-out option preferred, but some furniture delivery delayed

NC-v4 EQc4:Indoor air quality assessment
posted by  Erica Downs  on 

The project contractor intends to do a full flush-out prior to occupancy.  Most of the furniture will be installed prior to flush-out, but on particular oder has been delayed and may not arriv

12
Sustainability Director, Certifications & Compliance
Jacobs
LEEDuser Expert
469 thumbs up
Thu Jun 27, 2024, 3:48 pm
2
ESG consultant, LEED AP BD+C
Self Employed
LEEDuser Basic Member
36 thumbs up
Tue Jun 25, 2024, 7:27 pm

Purple Roof

NC-v4 SSc5:Heat island reduction
posted by  Edgar Arevalo  on 

Has anyone encountered a project where the client or other circumstances suggested we look into purple roof solution.  From the looks of it, it's a green roof solution with optimized stormwate

2
ESG consultant, LEED AP BD+C
Self Employed
LEEDuser Basic Member
36 thumbs up
Sun Jun 23, 2024, 11:50 pm

Entryway system

CI-v4 EQc1:Enhanced indoor air quality strategies
posted by  RAMON CHRISTOPHER MEDRANO  on 

I have a office space project, that will have an entryway system (walk off matt).

4
Sun Jun 23, 2024, 10:02 am
4
Sat Jun 22, 2024, 9:03 pm

Minimum Program Requirements - Must use a reasonable site boundary: site + building

NC-v4 MPR2:Must use reasonable LEED boundaries
posted by  Theresa Lehman  on 

This is a complex, multi-part question. An airport project is being phased and has multiple contracts. The scope includes replacing the runways and concrete around the terminals.

1
Fri Jun 21, 2024, 3:29 pm