NC-v4 EAc5:Renewable energy production
posted by  Johanna Scogin  on 

I'm confused as to the wording for solar gardens or community renewable energy systems (off-site): "The system is located with the same utility service area as the facility claiming the use." Does

2
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4454 thumbs up
Mon Feb 12, 2018, 9:19 pm

Addenda item from 1/5/2018 - Required Documentation table

NC-v4 EAc5:Renewable energy production
posted by  Erica Downs  on 

Hello - I was reviewing the Reference Guide addenda items, and there is one for this credit that just does not make sense.  It is regarding the Required Documentation table, page 439 in the RG

1
Fri Feb 9, 2018, 6:17 pm

Community choice aggregation (CCA) programs?

NC-v4 EAc5:Renewable energy production
posted by  Kristen Magnuson  on 

San Francisco's Public Utility Commission offers a currently-optional program called Clean Power SF. Electricity for the program is supplied by local renewable sources.

3
Fri Jan 19, 2018, 10:36 pm

energy used on-site vs sold energy

NC-v4 EAc5:Renewable energy production
posted by  LEEDme Lorenzi  on 

I’m reading the new version of the reference guide and I have some doubts concerning this credit. As example, within the LEED boundary electricity is produced by pv panels.

1
Thu Sep 11, 2014, 2:58 pm

Renewable Energy Production - point calculation

NC-v4 EAc5:Renewable energy production
posted by  juyew tang  on 

hi, i am new with this LEED. now i design for a new project. under this NC-V4, EAC5, is the point award still based on the below table? percentage of on-site renewable energy LEED point 1%

1
Thu Jul 20, 2017, 2:09 pm

Akvifer

NC-v4 EAc5:Renewable energy production
posted by  Sara Johansson  on 

Hello, We have a project located in Sweden. Does an akvifer that stores heating and cooling count as renewable energy? The akvifer has two sides - a cold and a warm.

1
Thu Nov 10, 2016, 4:51 pm

Solar PV Array Ownership

NC-v4 EAc5:Renewable energy production
posted by  Gray Bender  on 

Hello, I have a question about the ownership of a solar PV array, and how that effects this and any other credit.

1
Thu Sep 29, 2016, 8:51 pm

Aerothermal Energy

NC-v4 EAc5:Renewable energy production
posted by  Helena Garcia   on 

We're designing a system based on renewable energy installation for new construction. A part of this installation would performed by aerotermal energy.

1
Fri Jul 1, 2016, 1:49 pm

Third party in renewable energy

NC-v4 EAc5:Renewable energy production
posted by  soha yamani  on 

I am reading the below paragraph from the reference guide and i don't quite understand it , as it is really confused with the Green power credit?

7
BECxP, CxA+BE, LEED AP BD+C, O+M
Revitaliza Consultores
LEEDuser Basic Member
18 thumbs up
Fri Apr 21, 2017, 8:38 pm

ATES in combination with HP

NC-v4 EAc5:Renewable energy production
posted by  Ydo Schuuring  on 

We would like achieve points for the credit: Renewable Energy Production. The design team is considering an Aquifer Therma Energy Storage (ATES) in combination with a heatpump.

2
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4454 thumbs up
Fri Mar 17, 2017, 10:18 pm