LEED Health Care 2009 MR Prerequisite 2: PBT Source Reduction
Healthcare-v2009 MRp2:PBT source reduction - mercuryposted by William Kelly on
For Uload L-14 providing calculations for collection space and projected waste: 1.
High Pressure Sodium lamps--interior or exterior?
Healthcare-v2009 MRp2:PBT source reduction - mercuryposted by Maria Unruh on
The table MRp2-2, is this for HPS lamps for the entire project or for the interior only?
MRp2-2 : High Pressure Sodium Lamps
Healthcare-v2009 MRp2:PBT source reduction - mercuryposted by Ashley Johnson on
There are no HPS lamps installed on our project so how do I close this part of the form so that I can check for compliance and submit? I just put "0" quantity but will that suffice?
LEED Health Care 2009 MR Prerequisite 2: PBT Source Reduction
Healthcare-v2009 MRp2:PBT source reduction - mercuryposted by Andrea Breen on
For testing fly ash to be used in concrete, for the 5 ppb limit, are there any sampling requirements?
Providing dedicated area for mercury-containing products?
Healthcare-v2009 MRp2:PBT source reduction - mercuryposted by Richard Barlow on
We are trying to respond to Prelim. Design review comments on a LEED-HC v2009 project for an Inpatient Hospice and Palliative Care facility.
T2, T4, T6
Healthcare-v2009 MRp2:PBT source reduction - mercuryposted by Gustavo De las Heras Izquierdo on
This credit does not allow installing T9, T10 or T12 fluorescent lamps. This credit provides a criteria to specify T5 and T8 fluorescent lamps. Are there any requirement for T2, T4 and T6 fluores