EPA Target Finder rating tool

Schools-2009 EAp2:Minimum Energy Performance
posted by  Ameet AA  on 

Following requirement is stated even in the LEED 2009 School Alternative compliances path for project outside the U.S.(July 2012) "The project must establish an energy performance rating goal for

1
Mon Dec 3, 2012, 5:17 pm

Baseline Building Performance

Schools-2009 EAp2:Minimum Energy Performance
posted by  Justin Weisser  on 

In an all-electric building with a Geothermal Bore field and packaged Heat Pumps system, if the project wants to use an Indirect Gas fired Make-Up Air Unit for the Kitchen Exhaust Hood, will we hav

1
Thu Jun 19, 2014, 6:37 pm
1
Fri Jan 7, 2011, 10:22 pm

Trane TRACE's 40 plant limit.

Schools-2009 EAp2:Minimum Energy Performance
posted by  Kelsey Rightmer  on 

The school I am modeling has a vrf system served by dedicated outdoor air energy recovery units as well as packaged rooftop units.

1
Tue Jul 19, 2016, 4:32 pm

Water-Source Heat Pump part load efficiency

Schools-2009 EAp2:Minimum Energy Performance
posted by  eric jendro  on 

I am using HAP to model a system consisting of water-source heat pumps. I am required to input the ARI/ISO efficiency.

1
Fri Mar 9, 2012, 2:47 pm

Proper way to apply ASHRAE 62.1 to baseline model?

Schools-2009 EAp2:Minimum Energy Performance
posted by  Joseph Lewis  on 

I have a project where the proposed design has demand controled ventilation.

1
Wed Dec 4, 2013, 1:14 pm
1
Tue Aug 10, 2010, 12:23 am

Square Footage Discrepancy

Schools-2009 EAp2:Minimum Energy Performance
posted by  Michael Kros  on 

Our mechanical engneer/energy modeler just contacted me to ask about a discrepancy in our square footages from what we have entered on PIf2 on LEED Online, and what he has input in the energy model

1
Mon Mar 5, 2012, 11:03 pm

Section Table 1.4.2B- Fenestration

Schools-2009 EAp2:Minimum Energy Performance
posted by  soham babu  on 

when the frame effects are captured within the energy modeling software option the output results for vertical glazing assembly U value will vary based on window size.

2
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4454 thumbs up
Wed May 24, 2017, 6:45 pm