Two buildings on one project site
CS-2009 IEQp1:Minimum IAQ Performanceposted by James Lee on
Hi, I am James and am working on project with two buildings on one project site. In this case, should I fill out IEQp1 form separately like EAp2? Maybe someone already asked this question. But p
Naturally ventilated spaces
CS-2009 IEQp1:Minimum IAQ Performanceposted by Nader NAKIB on
I appreciate your interpretations on the ASHRAE 62.1 regarding the requirement for naturally ventilated spaces: 5.1.1 Location and Size of Openings: Naturally ventilated spaces shall be permanentl
Recilculation Class Air
CS-2009 IEQp1:Minimum IAQ Performanceposted by Luis Miguel Diazgranados on
Hi everybody, I am working in an office building project, core and Shell scope.
n/a
CS-2009 IEQp1:Minimum IAQ Performanceposted by Alan Viale on
Dear all, We are working on a mall with natural ventilation on the common areas (corridors).
Project size increase
CS-2009 IEQp1:Minimum IAQ Performanceposted by Silvia Ruiz on
Dear all In a project that we are certificating LEED C&S v3 the owner has modified the OPRs, specificly the project size and the MEP system. 1.
Growth and Erosion
CS-2009 IEQp1:Minimum IAQ Performanceposted by Adriana Hansen on
We have an HVAC system configured with ceiling plenum return. Is this plenum required to meet item (§ 5.5.1) Resistance to Mold Growth and (§ 5.5.2) Resistance to Erosion of ASHRAE 62.1?
Zone Air Distribution Effectiveness
CS-2009 IEQp1:Minimum IAQ Performanceposted by Noriko Nagazumi on
Let me confirm the following ASHRAE 62.1-2007 Zone Air Distribution Effectiveness (Ez) issue. Our project utilizes total heat exchangers for ventilation.
Occupant Density - Filling out the IEQp1 form
CS-2009 IEQp1:Minimum IAQ Performanceposted by Ron Dean on
Hello, I have two specific questions, please help me working them out. 1.
ASHRAE Standard
CS-2009 IEQp1:Minimum IAQ Performanceposted by ilkyaz ceren güçlü on
Hello, We are carrying out LEED certification of an office building.
Confidential lease agreements cannot be obtained
CS-2009 IEQp1:Minimum IAQ Performanceposted by John Mader on
Our project is an office building with some retail spaces on its lower floors that have already been leased.