EA Credit 5.1: Base Building Sub-metering
CS-2009 EAc5.1:Measurement and Verification—Base Buildingposted by Ian McCall on
Hello all, I am working on a large Core and Sheel project composed of office spaces and commercial centre (in France). The comercial centre is 5 stories high and occupied by one single tenant.
List energy end uses
CS-2009 EAc5.1:Measurement and Verification—Base Buildingposted by Mike D on
"The M and V Plan omits the table or listing of the project’s energy end uses as required by the form." However, the Plan we have submitted lists the following: Locations and types of energy meter
Description of quality assurance procedures.
CS-2009 EAc5.1:Measurement and Verification—Base Buildingposted by Rudolph Carneiro on
I recieved a comment for a project of mine and dont really know what they want exactly.
M&V period for LEED 2009 C&S projects for EAc5.1 + EAc5.2
CS-2009 EAc5.1:Measurement and Verification—Base Buildingposted by Philip Herriges on
The LEED reference guide is very particular in the language that they use to describe the intent and stragegies for EAc5.1 and 5.2 for C&S as being distinct from NC & Schools. For NC&
submit to leed-online compliance
CS-2009 EAc5.1:Measurement and Verification—Base Buildingposted by Ron Dean on
Good day, i wonder what is the time that I can submit the M&V plan for credit 5.1. May I submit it when the construccion is finished with the rest of the credits for C&S certification or I
EA 5,1
CS-2009 EAc5.1:Measurement and Verification—Base Buildingposted by Muhammad Faisal Azizullah Jaffar on
We are working on a mall project going ahead with the LEED CS GOLD.We are currently on tender stage and the client has suddently come up with the LEED requirement.
EAc5.1 and EAc5.2
CS-2009 EAc5.1:Measurement and Verification—Base Buildingposted by Christos Alexandrou on
Hello, I have been following the leeduser site and still trying to understand EAc5.1 and EAc5.2. I have been using them differently due to not having a clear explanation of the credits at usgbc.
EAc5.1 Review Report Help
CS-2009 EAc5.1:Measurement and Verification—Base Buildingposted by Redy Truccolo on
Hi, I received these technical advices but I don't really understand what they're asking me to add to the M&V Plan: 1.
Speculative Retail - No Meters Provided.
CS-2009 EAc5.1:Measurement and Verification—Base Buildingposted by Ciaran McCabe on
Im working on a mixed use development that consists of office space and retail units.
Emergency Power
CS-2009 EAc5.1:Measurement and Verification—Base Buildingposted by Brightworks Sustainability on
The engineer on my project is asking what exactly needs to be submetered and I'm having difficulty answering just because I'm not as familiar with the credit details.