Post a question or comment
Credit Filters
Measurement and Verification—Base Building
Filter by location
Forum
Topic
Replies
Recent

Energy Model Calibration by Post Construction data

CS-2009 EAc5.1:Measurement and Verification—Base Building
posted by  Gabriela Hernández Castillo  on 

Our Project is applying for M&V plan option D method 2, which let us calibrate the energy model with post construction measures.

1
Mon Jul 8, 2013, 6:37 pm

Separating lighting metering from plug load metering.

CS-2009 EAc5.1:Measurement and Verification—Base Building
posted by  Rudolph Carneiro  on 

I have seen many comments in this forum stating that plug loads should be metered seperately from lighting loads. I'm not sure if seperating these loads is actually necessary.

1
Fri Oct 25, 2013, 1:22 pm

Model Calibration - Margins for Error

CS-2009 EAc5.1:Measurement and Verification—Base Building
posted by  Ciaran McCabe  on 

For a new office building would it be acceptable to use these error margins for an M&V Report.

1
Fri Apr 21, 2017, 5:07 pm

Tenant Submetering connected to BMS?

CS-2009 EAc5.1:Measurement and Verification—Base Building
posted by  Marco Abdallah  on 

We are pursueing 5.1 Opt. 1 and 5.2 at a CS-project with 10 floors leasable to different tenants.

1
Fri Aug 24, 2012, 12:58 pm

EA Credit 5.1: Base Building Sub-metering

CS-2009 EAc5.1:Measurement and Verification—Base Building
posted by  Ian McCall  on 

Hello all, I am working on a large Core and Sheel project composed of office spaces and commercial centre (in France). The comercial centre is 5 stories high and occupied by one single tenant.

1
Wed Jun 4, 2014, 11:48 pm

List energy end uses

CS-2009 EAc5.1:Measurement and Verification—Base Building
posted by  Mike D  on 

"The M and V Plan omits the table or listing of the project’s energy end uses as required by the form." However, the Plan we have submitted lists the following: Locations and types of energy meter

1
Tue Jun 18, 2013, 1:55 pm

Description of quality assurance procedures.

CS-2009 EAc5.1:Measurement and Verification—Base Building
posted by  Rudolph Carneiro  on 

I recieved a comment for a project of mine and dont really know what they want exactly.

1
Sun Oct 13, 2013, 5:40 pm

M&V period for LEED 2009 C&S projects for EAc5.1 + EAc5.2

CS-2009 EAc5.1:Measurement and Verification—Base Building
posted by  Philip Herriges  on 

The LEED reference guide is very particular in the language that they use to describe the intent and stragegies for EAc5.1 and 5.2 for C&S as being distinct from NC & Schools. For NC&

1
Tue Jul 17, 2012, 4:26 pm

submit to leed-online compliance

CS-2009 EAc5.1:Measurement and Verification—Base Building
posted by  Ron Dean  on 

Good day, i wonder what is the time that I can submit the M&V plan for credit 5.1. May I submit it when the construccion is finished with the rest of the credits for C&S certification or I

1
Mon Dec 10, 2012, 4:30 pm

EAc5.1 and EAc5.2

CS-2009 EAc5.1:Measurement and Verification—Base Building
posted by  Christos Alexandrou  on 

Hello, I have been following the leeduser site and still trying to understand EAc5.1 and EAc5.2. I have been using them differently due to not having a clear explanation of the credits at usgbc.

1
Mon Oct 19, 2015, 8:59 pm