M&V period for LEED 2009 C&S projects for EAc5.1 + EAc5.2
CS-2009 EAc5.1:Measurement and verification - base buildingposted by Philip Herriges on
The LEED reference guide is very particular in the language that they use to describe the intent and stragegies for EAc5.1 and 5.2 for C&S as being distinct from NC & Schools. For NC&
submit to leed-online compliance
CS-2009 EAc5.1:Measurement and verification - base buildingposted by Ron Dean on
Good day, i wonder what is the time that I can submit the M&V plan for credit 5.1. May I submit it when the construccion is finished with the rest of the credits for C&S certification or I
EAc5.1 and EAc5.2
CS-2009 EAc5.1:Measurement and verification - base buildingposted by Christos Alexandrou on
Hello, I have been following the leeduser site and still trying to understand EAc5.1 and EAc5.2. I have been using them differently due to not having a clear explanation of the credits at usgbc.
EA 5,1
CS-2009 EAc5.1:Measurement and verification - base buildingposted by Muhammad Faisal Azizullah Jaffar on
We are working on a mall project going ahead with the LEED CS GOLD.We are currently on tender stage and the client has suddently come up with the LEED requirement.
M&V plan for cold and dark shell
CS-2009 EAc5.1:Measurement and verification - base buildingposted by Jatuwat Varodompun on
In case the system is yet designed, can CS project get the score in 5.1 and 5.2 by purely using tanant leasing agreement which has the M&V Plan as a reguirement to be responsible by tenants.
Monitoring VRF unit
CS-2009 EAc5.1:Measurement and verification - base buildingposted by Edmée Knight on
We are installing an air cooled VRF system with a DOAS in our building.
What to measure?
CS-2009 EAc5.1:Measurement and verification - base buildingposted by Marcio Alberto Casado Pereira on
We are working on a multiple building campus, it's a residential project.
Water Metering
CS-2009 EAc5.1:Measurement and verification - base buildingposted by Steve Gross on
Hello, My question is in regards to what need to be metered on the water side. Does the utility meter suffice or do I need to provide a meter for hot and cold water independently?
Calibrated vs actual energy use
CS-2009 EAc5.1:Measurement and verification - base buildingposted by Puteri Shireen Jahnkassim on
Dear all, What if the case is that the actual total energy use diverted only around 1 to 3 percent of the predicted energy during design? Is a calibrated energy simulation model still need by LEE