Energy Model Calibration by Post Construction data
CS-2009 EAc5.1:Measurement and Verification—Base Buildingposted by Gabriela Hernández Castillo on
Our Project is applying for M&V plan option D method 2, which let us calibrate the energy model with post construction measures.
Separating lighting metering from plug load metering.
CS-2009 EAc5.1:Measurement and Verification—Base Buildingposted by Rudolph Carneiro on
I have seen many comments in this forum stating that plug loads should be metered seperately from lighting loads. I'm not sure if seperating these loads is actually necessary.
Model Calibration - Margins for Error
CS-2009 EAc5.1:Measurement and Verification—Base Buildingposted by Ciaran McCabe on
For a new office building would it be acceptable to use these error margins for an M&V Report.
Tenant Submetering connected to BMS?
CS-2009 EAc5.1:Measurement and Verification—Base Buildingposted by Marco Abdallah on
We are pursueing 5.1 Opt. 1 and 5.2 at a CS-project with 10 floors leasable to different tenants.
EA Credit 5.1: Base Building Sub-metering
CS-2009 EAc5.1:Measurement and Verification—Base Buildingposted by Ian McCall on
Hello all, I am working on a large Core and Sheel project composed of office spaces and commercial centre (in France). The comercial centre is 5 stories high and occupied by one single tenant.
List energy end uses
CS-2009 EAc5.1:Measurement and Verification—Base Buildingposted by Mike D on
"The M and V Plan omits the table or listing of the project’s energy end uses as required by the form." However, the Plan we have submitted lists the following: Locations and types of energy meter
Description of quality assurance procedures.
CS-2009 EAc5.1:Measurement and Verification—Base Buildingposted by Rudolph Carneiro on
I recieved a comment for a project of mine and dont really know what they want exactly.
M&V period for LEED 2009 C&S projects for EAc5.1 + EAc5.2
CS-2009 EAc5.1:Measurement and Verification—Base Buildingposted by Philip Herriges on
The LEED reference guide is very particular in the language that they use to describe the intent and stragegies for EAc5.1 and 5.2 for C&S as being distinct from NC & Schools. For NC&
submit to leed-online compliance
CS-2009 EAc5.1:Measurement and Verification—Base Buildingposted by Ron Dean on
Good day, i wonder what is the time that I can submit the M&V plan for credit 5.1. May I submit it when the construccion is finished with the rest of the credits for C&S certification or I
EAc5.1 and EAc5.2
CS-2009 EAc5.1:Measurement and Verification—Base Buildingposted by Christos Alexandrou on
Hello, I have been following the leeduser site and still trying to understand EAc5.1 and EAc5.2. I have been using them differently due to not having a clear explanation of the credits at usgbc.