Timing of the post occupancy commissioning

CS-2009 EAc3:Enhanced Commissioning
posted by  R Jones  on 

Our project is a C&S project and we have a CXa onboard overseeing the commissioning process during design and construction.

3
Default Avatar
Vice President / Principal
2rw Consultants, Inc.
LEEDuser Basic Member
1 thumbs up
Thu Jan 2, 2014, 4:10 pm

Time for EAc3 submittal

CS-2009 EAc3:Enhanced Commissioning
posted by  Ron Dean  on 

Hello, Is it possible to submit the EAc3 form with the other ones for the Design Review Phase and Construction Review Phase?

2
Default Avatar
Sumac Inc.
LEEDuser Basic Member
20 thumbs up
Mon Nov 4, 2013, 7:23 pm

Multiple CxAs?

CS-2009 EAc3:Enhanced Commissioning
posted by  Michael Kros  on 

Can the commissioning agent listed on the form for EAp1 Fundamental Commissioning be different from the CxA listed on the form for EAc3 Enhanced Commissioning?

3
Default Avatar
Sumac Inc.
LEEDuser Basic Member
20 thumbs up
Thu Apr 11, 2013, 7:14 pm

Contract between Owner and CxA for EAc3 Form in leedonline

CS-2009 EAc3:Enhanced Commissioning
posted by  Ron Dean  on 

From the EAc3 form: ''Provide the contract between owner and CxA ensuring CxA involvement post-construction. Financial information may be redacted/omitted''.

2
Representative
Vermont House of Representatives
LEEDuser Expert
7780 thumbs up
Tue Apr 9, 2013, 2:10 pm