Choosing the correct rating system

Data-Centers-NC-v4 MPR3:Must comply with project size requirements
posted by  Dina El-Sady  on 

A data cebter building with the white area contributing to only 7% of the total BUA while the rest are offices, elec rooms , video rooms...etc , should it be treated as a data center rating system

0

Unoccupied Building

Data-Centers-NC-v4 MPR3:Must comply with project size requirements
posted by  Phillip Cook  on 

I am working on a datacentre that does not include any occupied areas and will have no regular staff on site - security and network support will be provided from an adjoining site.

3
Representative
Vermont House of Representatives
LEEDuser Expert
7780 thumbs up
Wed May 14, 2014, 11:42 pm