Replacing filters prior to occupancy
Schools-2009 IEQc3.1:Construction IAQ Management Plan—During Constructionposted by Ashley Love on
We have our preliminary review comments back and had a comment on this credit about the timeline of replacing the filters.
Construction - Indoor Air Quality V2009
Schools-2009 IEQc3.1:Construction IAQ Management Plan—During Constructionposted by Noelle Hunner on
Does the indoor air quality credit allow for propane powered lifts (inside the building) during construction? Or do they have to be battery powered only?
Filtration Media Documentation Table
Schools-2009 IEQc3.1:Construction IAQ Management Plan—During Constructionposted by Greengrade User on
The table in the form asks for the Location of th AHU, not the location that the temporary filter is installed.
Smoking During Construction
Schools-2009 IEQc3.1:Construction IAQ Management Plan—During Constructionposted by Jessica Diaz on
Our project is a school located in Puerto Rico, where the tropical climate allows for natural ventilation and where we don't use the HVAC system during construction.
temporary use of hvac during construction
Schools-2009 IEQc3.1:Construction IAQ Management Plan—During Constructionposted by Keelan Kaiser on
I have another question similar to above. We have a project that is substantially complete with construction, the cleaning crews are in right now. Only flooring remains to be installed.