NC-2009 IEQc3.1: Construction IAQ Management Plan—During Construction
LEEDuser is supported by our premium members, not by advertisers.
Go premium forTo post a comment, you need to register for a LEEDuser Basic membership (free) or login to your existing profile.
Calie Gihl
Design EngineerLEEDuser Expert
19 thumbs up
July 13, 2018 - 4:25 pm
Hi Chad,
The contractor should review the requirements of the updated SMACNA guidelines and ensure that his plan still meets these requirements. Then, referencing the up to date guidelines will not be an issue.
Sorry for the delay in response - good luck on your project.
Calie