I am exploring additional credits and may possibly apply for a design pilot credit during the construction phase of our project. Our project is being submitted as a split review. The design phase is ready to submit now and I would rather not delay this. Can I submit documentation on a pilot credit at any time or do Design pilots need to be submitted with the design phase and Construction pilots with the Construction phase?
You rely on LEEDuser. Can we rely on you?
LEEDuser is supported by our premium members, not by advertisers.
Go premium for
Batya Metalitz
Technical Director, LEEDUSGBC
LEEDuser Expert
318 thumbs up
December 16, 2014 - 1:08 pm
Hi Alfred
You can submit pilot credits during either review. Pilot credits aren't specifically design or construction. However, be sure to read through the pilot credit early on to make sure that anything that needs to be completed early on (during schematic design or prior to construction for example) gets done and documented at the appropriate time.