The project is over 50,000 square feet and we are the owner and commissioning authority and designer of record.
What commissioning services are we allowed to provide, fundamental or enhanced?
Forum discussion
NC-2009 EAp1: Fundamental Commissioning of Building Energy Systems
The project is over 50,000 square feet and we are the owner and commissioning authority and designer of record.
What commissioning services are we allowed to provide, fundamental or enhanced?
LEEDuser is supported by our premium members, not by advertisers.
Go premium forTo post a comment, you need to register for a LEEDuser Basic membership (free) or login to your existing profile.
Dave Hubka
Practice Leader - SustainabilityEUA
LEEDuser Expert
530 thumbs up
June 26, 2014 - 10:25 am
found it!
LI #10278 answered my question.
Scott Bowman
LEED FellowIntegrated Design + Energy Advisors, LLC
LEEDuser Expert
519 thumbs up
June 26, 2014 - 10:29 am
Sorry David, have not been keeping up! If you are the owner, and have qualified staff, then you can certainly do enhanced commissioning. Our firm project was not as large, but I performed those functions.
The fun part is one Principal (me) telling another Principal (the CFO) that changes should be made!
Dave Hubka
Practice Leader - SustainabilityEUA
LEEDuser Expert
530 thumbs up
June 26, 2014 - 10:36 am
No worries Scott, I am sure you are plenty busy, (quite honestly I do not know how Marcus Sheffer keeps up with all the energy modeling questions).
You hit the nail on the head with the Principal to Principal comment. This specific project is our 50,000+ sf corporate office that pursued LEED CI. We needed to be very delicate when delivering our design review comments to our executive team. :)