If a project installs one meter for the building (essentially collectively metering indoor plumbing fixtures and domestic hot water) and another meter for irrigation water, what are the ramifications on prerequisite and credit compliance?
You rely on LEEDuser. Can we rely on you?
LEEDuser is supported by our premium members, not by advertisers.
Go premium for
Tristan Roberts
RepresentativeVermont House of Representatives
LEEDuser Expert
11477 thumbs up
December 13, 2017 - 11:06 am
Ryan, it sounds like you would meet the prerequisite requirements, but not the credit.