I've seen previous discussions as to equipment clean-up water waste not being applicable to this credit, but in our project, water and aggregate is generated by the installation of materials. My question is this: with a sprayed-on cementitious fireproofing, waste aggregate and water is hauled off by a washout waste contractor and is taken to a ready-mix recycling facility. There are haul tags to substantiate this. Can we include this material in MR 2 calcs? I would say yes, and there's no downside. Do others agree?