Hi,
I am working on a LEED project within the UK, and I am trying to understand the alternative paths to ASHRAE Guideline 0-2013, ASHRAE Guideline 1.1–2007 for HVAC&R System, ASHRAE 90.1-2016 to meet EAp1, EAp2.
Many thanks,
Ali
Forum discussion
CI-v4 EAp1: Fundamental commissioning and verification
Hi,
I am working on a LEED project within the UK, and I am trying to understand the alternative paths to ASHRAE Guideline 0-2013, ASHRAE Guideline 1.1–2007 for HVAC&R System, ASHRAE 90.1-2016 to meet EAp1, EAp2.
Many thanks,
Ali
LEEDuser is supported by our premium members, not by advertisers.
Go premium forTo post a comment, you need to register for a LEEDuser Basic membership (free) or login to your existing profile.
For a building with individual systems per unit, does every single system need to be commissioned?
What kinds of projects must the CxA demonstrate experience on?
What level of authority does the CxA have towards correcting inaccurate or erroneous construction?
Can the CxA be a member of the design or construction team?
Karen Elliott
LEED AP ID+C & BD+CEcoteric Ltd
1 thumbs up
February 15, 2019 - 10:43 am
Hi Alexander
We are in the UK too. When I asked the question of USGBC about 3 years ago the answer was no, but that might have changed in the last few year? We always use ASHRAE 90.1. TAS & IES both have ASHRAE bolt ons for doing the modelling.
Karen.
Scott Bowman
LEED FellowIntegrated Design + Energy Advisors, LLC
LEEDuser Expert
519 thumbs up
August 11, 2019 - 6:30 pm
Sorry for the incredibly late comment. Since Cx is about process, I think you would still need to comply with the standards. This is not about metric versus imperial.