If our client who own the entire building would like to do the fitout for only 1 floor. The toilet is out of fitout scope.
The client would like to get LEED CI certified.
Is the project eligible to be exempt from WEp1?
You rely on LEEDuser. Can we rely on you?
LEEDuser is supported by our premium members, not by advertisers.
Go premium for $15.95 »
Carlie Bullock-Jones
PrincipalEcoworks Studio
LEEDuser Expert
220 thumbs up
September 13, 2012 - 9:46 am
Hi Sompoche,
LEED-CI projects without plumbing in their scope of work are exempt from WEp1.