Forum discussion

NC-2009 EAc2:On-Site Renewable Energy

Timing outsourced solar plan on-site / the building

Hi All,

I have a question regarding the development of a new building on a existing plant. Prior to the construction a solar plant will be installed on-site (not a building) and connected to the building. The system is outsourced to a third party and will be operational by September 2018. The construction of the building will take place later. Is this time issue a problem for obtaining this credit (other demands like the contract will be in place)?

0

You rely on LEEDuser. Can we rely on you?

LEEDuser is supported by our premium members, not by advertisers.

Go premium for $15.95  »

Mon, 04/23/2018 - 15:42

No it should be fine as long as the project meets the requirements for utilizing power from this system.

Add new comment