Art classrooms are considered both in Tab. 6-1 and in Tab. 6-4. If we respect Tab. 6-4, could we avoid the verification of Tab. 6-1 (i.e. could we avoid the outdoor air supply)?
You rely on LEEDuser. Can we rely on you?
LEEDuser is supported by our premium members, not by advertisers.
Go premium for
Christopher Schaffner
CEO & FounderThe Green Engineer
LEEDuser Expert
963 thumbs up
April 20, 2017 - 11:37 am
Why you would want to do that?
My reading of 62.1-2010 is that you must meet both requirements. And what goes out must be replaced somehow.