Although it is the requirement of the Commissioning Agent to develop the Systems Manual, Operation & Maintenance Systems manuals, can he/she delegate that responsibility to the General Contractor?
You rely on LEEDuser. Can we rely on you?
LEEDuser is supported by our premium members, not by advertisers.
Go premium for
Chris Ladner
PartnerViridian
261 thumbs up
November 18, 2011 - 11:13 am
A good approach to this requirement is for the CxA to define the format of these close-out documents and make sure each team member is clear on what their responsibility is related to the manuals. The Cx documents should comprise a large portion of the systems manual, but we have found that the contractor is best suited to compile the majority of the IOM’s, etc.