Forum discussion

NC-2009 PIf3:Occupant and Usage Data

Submittal recomendation.

We are currently close to finishing all credit requirements. Do you recomend to submitt al information for review as it is completed or wait to have all ready and submitting it all at once?

0

You rely on LEEDuser. Can we rely on you?

LEEDuser is supported by our premium members, not by advertisers.

Go premium for $15.95  »

Wed, 08/14/2013 - 21:50

Daniel, it depends on where you are in the schedule. We don’t have the option to submit credits individually for review. If construction is not complete, you can submit all the "design phase credits" in one batch and have those reviewed. Then, when construction is complete you know how you did before you submit all the construction phase credits. If construction is complete, it's probably simpler to do the combined design and construction review and submit all the credits at once.

Add new comment

To post a comment, you need to register for a LEEDuser Basic membership (free) or login to your existing profile.