Forum discussion

CI-2009 EAc3:Measurement and Verification

submetering equipment

our Project is LEED CI v3 at credit EA c3, what is process uses ( electric) and process uses (fuel) ?????? another question , at our tenant space we have boiler fuel operated to supply under floor heating and domestic hot water , what type sub meters we need to measure the energy consumption ????? Thanks

0

You rely on LEEDuser. Can we rely on you?

LEEDuser is supported by our premium members, not by advertisers.

Go premium for $15.95  »

Wed, 04/02/2014 - 14:35

Process loads are those that are not regulated by ASHRAE 90.1 such as plug loads, gas cooking, etc. Which case are you pursuing? For Case 1 the Reference Guide is pretty clear about what needs to be submetered, see Table 2 on page 191. The type of meter depends on the fuel source. What is the boiler fuel?