our Project is LEED CI v3
at credit EA c3, what is process uses ( electric) and process uses (fuel) ??????
another question , at our tenant space we have boiler fuel operated to supply under floor heating and domestic hot water , what type sub meters we need to measure the energy consumption ?????
Thanks
Marcus Sheffer
LEED Fellow7group / Energy Opportunities
LEEDuser Expert
5931 thumbs up
April 2, 2014 - 10:35 am
Process loads are those that are not regulated by ASHRAE 90.1 such as plug loads, gas cooking, etc.
Which case are you pursuing? For Case 1 the Reference Guide is pretty clear about what needs to be submetered, see Table 2 on page 191. The type of meter depends on the fuel source. What is the boiler fuel?