We have an hi-rise office building with Chiller and AHUs system. We plan to 3 AHUs per floor.

1. My understanding is that we need to provided "only the central system" which allow tanant submetering. Tenant can themselve install the meter (via leasing agreement). Am I correct?

2. What about cooling energy from the chillers? Is it OK to just write the method to estimate cooling energy using floor area and time of operation of each tanants. If we do not monitor this cooling component, it seems that we do not cover all "eletric" components although the cooling enegry will be reflect usage at chiller plants.