We are working on a project precertification (v2009) and I was suprised that the precertification credit form requires a description of measures that will be implemented at the project site.
Can someone provide guidance, what to do if a GC has not been appointed yet (and it is the contractor's responsibility to plan and manage those measures)? Thank you.
You rely on LEEDuser. Can we rely on you?
LEEDuser is supported by our premium members, not by advertisers.
Go premium for
Michael DeVuono
Regional Stormwater LeaderArcadis North America
LEEDuser Expert
187 thumbs up
August 18, 2014 - 7:58 am
If your GC is developing your E&S plan you have two options:
Develop the plan prior to appointing a GC
Submit after the GC is appointed and the plan developed.
There really is no other way around this.