We are working on a project precertification (v2009) and I was suprised that the precertification credit form requires a description of measures that will be implemented at the project site. Can someone provide guidance, what to do if a GC has not been appointed yet (and it is the contractor's responsibility to plan and manage those measures)? Thank you.

0

You rely on LEEDuser. Can we rely on you?

LEEDuser is supported by our premium members, not by advertisers.

Go premium for $15.95  »

Mon, 08/18/2014 - 11:58

If your GC is developing your E&S plan you have two options: Develop the plan prior to appointing a GC Submit after the GC is appointed and the plan developed. There really is no other way around this.