NC-2009 SSc7.1:Heat Island Effect—Non-Roof

SRI Testing for Concrete?

Do you have to submit concrete for SRI testing if in the LEED-NC reference table it is listed as 35 for (new gray)? Also, do they count the intitial value or the aged 3 year value?

2

You rely on LEEDuser. Can we rely on you?

LEEDuser is supported by our premium members, not by advertisers.

Go premium for $15.95  »

Mon, 10/31/2011 - 20:58

Christina, you can use the default SRI values from the LEED Reference Guide (as we note above in the Checklists tab, FYI).If it's new concrete you can use the new value.

Tue, 05/08/2012 - 20:30

we are thinking about a light concrete roof over some of our parking areas in one of our projects. Could we use the default SRI values for new concrete to document compliance with Option 2?

Wed, 08/22/2012 - 15:56

The default SRI for new gray concrete has been changed to 38 per the addenda.