Forum discussion

CS-2009 IEQc3:Construction IAQ Management Plan—During Construction

SMACNA Ductwork Protection Guidelines

In order to qualify for this credit is it acceptable if the duct work is wrapped once it arrived on site OR should it arrive pre-wrapped. Is it acceptable if we wrap the duct work end in plastic in a designated clean part of the site upon arrival.

0

You rely on LEEDuser. Can we rely on you?

LEEDuser is supported by our premium members, not by advertisers.

Go premium for $15.95  »

Tue, 11/08/2016 - 23:52

Yes. That sounds like a thoughtful, conscientious plan. The intent is to prevent construction debris/dust from getting into ducts during construction activities. Describe your methodology in your IAQ Management plan.

Add new comment