You rely on LEEDuser. Can we rely on you?
LEEDuser is supported by our premium members, not by advertisers.
Go premium forForum discussion
NC-2009 EAp2: Minimum Energy Performance
LEEDuser is supported by our premium members, not by advertisers.
Go premium forTo post a comment, you need to register for a LEEDuser Basic membership (free) or login to your existing profile.
A portion of our building envelope is historic. Can we exclude it from our model?
For an existing building, do I need to rotate the model?
Our process load is higher than 25%. Do we have to justify that?
Our local code references ASHRAE 90.1-2010. Should I use that for my documentation, or 90.1-2007?
Can mezzanines open to floors below be excluded from the energy model?
How do I provide a zip code for an international location?
For a project outside the U.S., how do I determine the climate zone?
For a project outside the U.S., how do I determine the Target Finder score?
Do hotel rooms need automatic light shut-off control?
How commonly are the 90.1 mandatory compliance forms submitted as part of EAp2/EAc1?
The Section 9 space-by-space method does not include residential space types. What should I use?
Can the Passive House Planning Package (PHPP) be used to energy model for LEED?
Which baseline HVAC system do I use if my building has no heating or air conditioning?
Our project has a diesel backup generator. Should we include it in our energy model?
Can SHGC be higher in the proposed than in the baseline model?
Marcus Sheffer
LEED Fellow7group / Energy Opportunities
LEEDuser Expert
5909 thumbs up
April 9, 2015 - 10:14 am
SHGC is not a mandatory provision so it is available for trade off. You can exceed this prescriptive value in the Proposed model and use 0.25 in the Baseline model.